Miramar Water Treatment Plant Upgrade and Expansion Project

Project Description

Aerial view of Miramar Water Treatment Plant

The City of San Diego Water Department's Miramar Water Treatment Plant (WTP) began operation in 1962. The treatment plant is the sole provider of drinking water to an estimated 500,000 customers in the northern section of the City. The plant is located in the Scripps Miramar Ranch community on the shore of Miramar Reservoir, which is also a popular recreation site. Currently the plant produces 140 million gallons of drinking water a day (mgd). Water sources for the treatment plant are imported water from northern California and the Colorado River brought into San Diego by the San Diego County Water Authority and local rainfall captured in the reservoir.

The upgrade and expansion project began in summer 1998 with construction starting in May 2001 with the Early Start Improvements Phase I. The project is expected to be completed in early 2013. The Miramar Water Treatment Plant Upgrade and Expansion Project includes a new rapid mix facility, installing new de-aeration basins, disinfection facilities, new chemical facilities, new and refurbished administration facilities, flocculation and sedimentation basins, washwater recovery system and water filters.

Project Begins (Design Phase): Summer 1998

Construction Begins: April 2001

Construction Complete: Early 2013

Project Benefits

Project Need

Contract Schedule

Contract Name and Overview Construction Timeframe
Early Start Improvements Phase I
  • Construct distribution pipelines, valve vault, tunnel and untreated (raw) water pump station modifications
April 2001 – Jan. 2003
Early Start Improvements Phase II
  • Connect distribution pipeline to existing clearwells
  • Prepare surfaces and grade for work in subsequent contract
  • Construct temporary chemical facilities and new San Diego County Water Authority water feed pipeline
Sept. 2002 – Feb. 2005
Contract A
  • Construct new filters, rapid mix facility, de-aeration basin
  • Construct chlorine facility, ozonation structure, chemical buildings
  • Build the administration building and other structures
  • Build mechanical and electrical equipment and piping connecting the new facilities
Aug. 2003 – Dec. 2007
Contract B
  • Construct new high-efficiency flocculation and sedimentation basins
  • Demolish existing filters, flocculation and sedimentation basins
  • Demolish existing operations building and other structures
Nov. 2007 – Dec. 2009
Contract C
  • Construct ozone disinfection facilities
May 2008 – Mar. 2010
Contract D
  • Standard Urban Stormwater Mitigation Plan
  • Retaining Wall and Drainage
  • Landscaping and Water Conservation Irrigation System
  • Fencing
October 2011-Early 2013

Construction Overview and Updates

Contact Us

If you are interested in learning more about this project, please e-mail us at engineering@sandiego.gov.