Rose Creek Bikeway and Pedestrian Bridge Project
Project Background
This project is the vital missing link between the existing regional bicycle network that connects the existing bicycle facility along Pacific Beach Drive to the Class I bikeway at North Mission Bay Drive. This project is described and in conformance with the Mission Bay Master Plan and the Pacific Beach Master Plan. This bridge and bikeway will create a safe and convenient route over Rose Creek and significantly help minimize the use of Grand Avenue as the only route over the Creek.
Project Overview
The project includes the construction of a 260-foot bridge over Rose Creek connecting North Mission Bay Drive to Pacific Beach Drive. In addition, a total of 0.28 miles of new bikeway will be constructed from Rose Creek to Lee Street, between the properties of Mission Bay High School and Campland.
Benefits
- The bridge and bikeway will provide an alternate means of transportation for residents and visitors to and from Mission Bay, the beaches, school, work, and the adjacent businesses
- The bridge will provide a safer route for bicyclists and pedestrians over Rose Creek
- Traffic and congestion will be reduced on Grand Avenue currently serving as the only route over Rose Creek
- The new Rose Creek Bridge will be state-of-the-art construction and aesthetically enhancing to the surrounding landscape
Cost
The construction contract is $2,900,000.
Schedule
| Construction Start: | April 2011 |
| Construction Finish: | Spring 2012 |