Sewer Group Replacement 725

Background

Sewer mains across the City of San Diego have served their design life. These mains are old and have become unable to service the City’s growing demand. This project will replace old, deteriorating and under capacity sewer mains in the SDSU College area.

Project Overview

Sewer Group 725 consists of the installation of 4,622 lineal feet of 8-inch sewer mains and manholes, as well as the rehabilitation of other sewer mains. The areas and limits of work are as follows:

The project also involves surveying, potholing for existing utilities, asphalt saw cutting of trenches, and slurry sealing of roads. Road closures, detours, temporary “No Parking” and restricted access might be implemented during working hours.

Construction Schedule

Construction is scheduled to begin October 26th 2009 and is estimated to complete in the spring of 2010.

Normal working hours will be Monday through Friday, 8:30 a.m. to 3:30 p.m.

Cost

Total estimated cost of the project is $1, 347,370.

Important Documents

Contact Us

If you would like to receive more information about this project, please e-mail us at engineering@sandiego.gov.