Infrastructure Expense Summary - Attachment A-1

 

 

Project Infrastructure Improvements Total
Project Costs
1. Public Roadways $8,265,196
2. Ballpark parcel Site Work (Demo & Abatement) $2,190,015
3. Park and Plaza Site Work & Improvements $2,553,735
4. Parking Improvements  
  Surface Parking Improvements  
    D1$646,000 
    D2$530,000 
    P5$500,000 
    P6$500,000 
    P7$500,000 
    P8$500,000 
  Bldg. Abatement & Demo for P1& P5-P8 lots$1,811,500 
  Structured Parking Improvements (P1)$10,000,000 
  Parking Equipment Allowance$750,000 
    Parking Improvements Subtotal: $15,737,500
5. Subsurface Hazardous Materials Allowance $1,000,000
6. Transit System Improvements $400,000
7. Site Utilities $14,376,000
8. Permits & Fees3%$1,335,673
9. Architecture & Engineering8%$3,561,796
10. Escalation10%$4,452,245
11. Planning & Predevelopment $2,590,000
12. City Project Administration $1,281,000
13. Contingency $3,845,740
  Total Infrastructure Costs/Uses of Funds $61,588,900

Memorandum of Understanding
Attachments:
Attachment A - Map of Infrastructure Improvements
*Attachment A1 - Infrastructure Expense Summary
Attachment A2 - Roadway Improvement Detail
Attachment B - Land Acquisition Parcels
Attachment B1 - Land Acquisition Summary
Attachment B2 - Summary of 5,000 Parking Spaces
Attachment C - Hotel Credit Zone
Attachment C1 - Substitute Ancillary Retail Development
Attachment D - RFP/RFQ Zone
Attachment E - General Target Timetable
Attachment F - Padres Protection of Revenues
Attachment G - Ballpark Protection Zone