City Seal The City of San Diego
HomeContact the City
City Seal
City Seal Business City Hall Community Departments Information Leisure Services A-Z Visiting
Engineering & Capital Projects / Underground Utilities Program
Engineering & Capital Projects HomeUnderground Utilities Program HomeOverview/HistoryUnderground ProcessScheduleDocumentsProject UpdatesFrequently Asked QuestionsContact Information
Underground Process Photo of Underground Power Line

Construction Process

Construction of underground utility systems and the subsequent removal of overhead utility systems typically takes between 18 and 24 months for most large projects. This process consists of four phases: Trenching, cabling, cut-overs and pole removal.

Phase I: Trenching

Photo of Cable in Trench In this phase, crews create a trench and install round plastic conduit below the surface of the roadway. The crews will also trench up to each of the homes and businesses at this time. This is the most community impacted phase of construction and typically can be expected to last 9 to 12 months. On average, most trenching crews can perform 100 feet of trenching or more per day, so trenching operations can be expected to be in front of any particular home or business for just a few days. During this phase, a separate electrical contractor will be working on the electrical panels of the individual homes and businesses in order to prepare them to receive the new underground service.

Phase II: Cabling

Photo of Boxes and Pedestal In this phase, technicians place new utility lines within the new conduits. The new lines are then energized and brought into service. Residents will most likely hardly notice the few crews who perform this work as this work has very little community impact. This phase can be expected to last between 6 to 9 months.

During this phase, residents will probably notice the new transformer and cable boxes and pedestals being placed above ground near the curbs. These boxes are necessary for the underground system and cannot be placed underground for system reliability reasons.

Phase III: Cut-Overs

Once a new underground system is in place and energized, and all properties have been prepared to receive underground service, all properties are switched over from the overhead lines to the new underground systems. This phase will typically take one to two months.

Phase IV: Pole Removal

Photo of Pole Removal When 100% of properties have been switched over to the new underground system, the overhead systems are de-energized and removed. This phase can last two to three months.



| Engineering & Capital Projects Home | Underground Utilities Program Home | Overview/History | Top of Page |
| Underground Process | Schedule | Documents | Project Updates | Frequently Asked Questions | Contact Information |
Site Map Privacy Notice Disclaimers