Total Amount Awarded: $0.00

The requisite justification memo for all contracts identified below as sole-source contracts is included in the PDF document for each contract. It is available for viewing by clicking on the Contract Number for the desired project.

To comply with the requirements of Proposition A and the San Diego Sunshine Act, the contracts listed here are being made available to help ensure that the public has access to government information and policymaking information. These resources provide, in a searchable format, the text of all construction project contracts entered into by the City valued at more than $25,000, from July 1, 2021 through June 30, 2022.

To view a contract, click on the Contract Number for the desired project.

Contract Number Contract Name Award Date Award Amount Contractor No. of Bidders Contact
K-22-2046-EMR-1 Emergency Construction Services For: Repair of Traffic Signal at Balboa Avenue and Genesee Avenue Intersection 01/13/2021 $130,000.00 Flatiron West, Inc. 1 Juan E. Espindola
K-22-2075-DBB-3

Slurry Seal Group 2124

06/29/2022 $5,453,874.87 Pavement Coatings Co. 2 Juan E. Espindola
K-22-2114-EMR-3

Emergency Design and Construction Services For: 4101 Pacific Hwy Pump Station C

06/30/2022 $3,500,000.00 JR Filanc Construction Company, Inc. N/A Brittany Friedenreich
K-22-2070-JOC-3 - South

JOC Paving South

06/08/2022 $10,000,000.00 Hazard Construction Company 4 Brittany Friedenreich
K-22-2108-EMR-3

Pump Station N Storm Drain Emergency at 914 Santa Clara

06/21/2022 $4,500,000.00 Orion Construction Corporation N/A Ron McMinn
K-22-2071-DBB-3 Mission Center Canyon A Sewer Main Replacement 06/21/2022 $1,889,563.08 Burtech Pipeline Incorporated 7 Juan E. Espindola
K-22-2063-DBB-3 Sewer & AC Water Group 793 06/21/2022 $7,894,858.00 KTA Construction Inc. 6 Brittany Friedenreich
K-22-2088-DBB-3 AC Water & Sewer Group 1050 06/21/2022 $12,526,278.54 Burtech Pipeline Incorporated 5 Rosa Riego
K-22-2085-EMR-3 Balboa Park Pipeline North of I-5 Emergency Repair 06/14/2022 $2,000,000.00 Cass Construction, Inc. N/A Ron McMinn
K-22-2062-JOC-3-N Building Improvements - North 06/10/2022 $4,500,000.00 LDCO, Inc. 8 Ron McMinn
K-22-2062-JOC-3-S Building Improvements - South 06/10/2022 $4,500,000.00 Exbon, Inc. 8 Ron McMinn
K-22-2054-DBB-3 Otay WTP Basin Restoration 06/07/2022 $1,979,470.00 Abhe & Svoboda, Inc. 5 Ron McMinn
K-22-2070-JOC-3 - North JOC Paving North 06/08/2022 $10,000,000.00 Ramona Paving & Construction Corp. 4 Brittany Friedenreich
K-22-1915-DBB-3 Plumosa Park Series Circuit Conversion 06/03/2022 $824,280.00 Blue Pacific Engineering & Construction 4 Juan E. Espindola
K-22-2099-SLS-1 Sole-Source Construction for Long-Term Maintenance and Monitoring for 3035 Udall Street Storm Drain 05/31/2022 $63,908.43 RECON Environmental, Inc. 1 Juan E. Espindola
K-22-2081-EMR-3 Caminito San Pablo Emergency Storm Drain Repair 05/27/2022 $500,000.00 TC Construction Company In N/A Brittany Friedenreich
K-22-2047-DBB-3 AC Water & Sewer Group 1052 05/23/2022 $9,903,451.10 Burtech Pipeline Incorporated 4 Rosa Riego
K-22-1962-DBB-3 Hickman Field Athletic Area 05/17/2022 $7,946,695.00 Blue Pacific Engineering & Construction 5 Juan E. Espindola
K-22-1950-DBB-3-A Pacific Highlands Ranch Branch Library 05/12/2022 $20,184,623.00 Soltek-ECC A Joint Venture 3 Juan E. Espindola
K-22-2069-DBB-3 Curb Ramp Improvement Group 1701 05/10/2022 $1,499,229.08 LC Paving & Sealing, Inc. 5 Rosa Riego
K-22-2012-DBB-3-A Adams Ave (1620) Storm Drain Replacement 04/26/2022 $547,890.00 New Century Construction, Inc. 7 Rosa Riego
K-22-2035-DBB-3-A Balboa Park Federal Building Improvement 04/13/2022 $1,079,850.00 Chambers Inc. dba Roof Construction 8 Ron McMinn
K-22-2068-DBB-3 Tierrasanta Improv 1 Sewer 04/07/2022 $1,567,000.00 Burtech Pipeline Inc. 2 Brittany Friedenreich
K-22-2048-DBB- 3

Slurry Seal Group 2123

03/29/2022 $5,120,120.00 VSS International, Inc. 3 Ron McMinn
K-22-2083-DBB-3

Lobrico Ct. Storm Drain

03/16/2022 $675,520.60

Palm Engineering Construction Co., Inc.

14 Brittany Friedenreich
K-22-2031-EMR-1

Pump Station 11 Generator Repair

03/14/2022 $100,000.00 TC Construction Co., Inc. N/A Ron McMinn
K-22-2078-EMR-3 Pump Station 1 #4 Emergency 03/15/2022 $1,500,000.00 Cass Construction Inc. dba Cass Arrieta N/A Brittany Friedenreich
K-22-2066-EMR-3 4182 60thSt and 5973 Alta Mesa Way Emergency 02/15/2022 $2,700,000.00 J.R. Filanc Construction, Inc. 1 Juan E. Espindola
K-22-2052-EMR-3 3405 Kite Street Storm Drain Emergency 02/01/2022 $1,500,000.00 Hazard Construction Company 1 Juan E. Espindola
K-22-2025-DBB-3-A Clairemont Mesa East Pipeline Improvement 1 01/31/2022 $8,000,730.08 Ortiz Corporation 6 Rosa Riego
K-22-2055-EMR-3 Emergency Repairs to the Otay 2nd Pipeline at La Media Road 01/31/2022 $500,000.00 TC Construction Company, Inc. N/A Brittany Friedenreich
K-21-2026-DBB-3 AC Water and Sewer Group 1036 01/27/2022

$6,029,338.60

Palm Engineering & Construction Co., Inc. 6 Ron McMinn
K-22-1977-DBB-3-A Slurry Seal Group 2024 01/27/2022 $4,605,610.28 Pavement Coatings, Co. 3 Celina Suarez
K-22-2053-EMR-3 Point Loma Wastewater Treatment Plant Digesters Emergency Repairs 01/27/2022 $5,000,000.00 Orion Construction Corporation N/A Celina Suarez
K-22-2044-EMR-2 3984 Pacific Hwy Pump Station L Emergency 12/23/2021 $425,000.00 Cass Arrieta 1 Rosa Riego
K-22-2043-EMR-3 Ocean Beach Pier Improvements Emergency 12/14/2021 $450,000.00 TC Construction Co., Inc. 1 Ron McMinn
K-22-1994-SLS-3 Pump Station 64 Motor Starter Replacement 12/10/2021 $500,000.00 Eaton Corporation 1 Juan E. Espindola
K-21-1791-DBB-3-A North City Water Reclamation Plant Flow Equalization Basin 11/17/2021 $11,886,000.00 Kiewit Infrastructure West Co. 5 Juan E. Espindola
K-21-1919-DBB-3 MBGC Irrigation & Electrical Upgrades + MBGC Clubhouse Demo/Prtbl Building Instl 11/16/2021 $9,199,700.00 3-D Enterprises, Inc. 3 Brittany Friedenreich
K-22-2027-DBB-3 Riviera Del Sol Neighborhood Park 11/16/2021 $5,524,537.00 Whillock Contracting, Inc. 10 Brittany Friedenreich
K-21-1986-DBB-3 Wangenheim Neighborhood Park Joint Use Facility 11/16/2021 $6,834,000.00 Tri-Group Construction & Development, Inc. 11 Juan E. Espindola
K-22-2037-EMR-3 Campanile Wy Storm Drain Replacement 11/08/2021 $1,500,000.00 Orion Construction Corporation N/A Celina Suarez
K-22-2036-EMR-3 4617 Antioch Pl CMP SD Emergency 11/01/2021 $1,200,000.00 Orion Construction Corporation N/A Celina Suarez
K-21-1981-DBB-3 Santa Clara Improvements Playground and Comfort Station 11/02/2021 $1,380,888.00 Marcon Engineering, Inc. 11 Brittany Friedenreich
K-21-2029-SLS-2 Long Term Maintenance and Monitoring Crest Canyon Park Emergency SD Replace 11/05/2021 $439,000.00 Habitat Restoration Sciences, Inc. 1 Juan E. Espindola
K-21-1970-DBB-3 El Cajon Blvd-Highland to 58th Improvements 11/01/2021 $885,305.00 HMS Construction, Inc. 6 Rosa Riego
K-22-2038-EMR-3

Emergency Design and Construction Services: Udall Street Storm Drain Replacement

10/25/2021 $1,000,000.00 TC Construction, Inc. N/A Rosa Riego
K-21-2039-EMR-2 Emergency Repair of Sewer Pump Station 1, Pump 5, and 6 10/21/2021 $500,000.00 Orion Construction Corporation 1 Juan E. Espindola
K-22-2040-EMR-3 Mississippi Street CMP Storm Drain Emergency 10/14/2021 $526,000.00 Cass Construction, Inc. dba Cass Arrieta N/A Ron McMinn
K-21-2017-DBB-3 Accelerated Manhole Referral Group 1 10/12/2021 $1,026,647.00 Palm Engineering Construction Co., Inc. 5 Celina Suarez
K-21-1978-JOC-3 JOC Mechanical 10/06/2021 $4,500,000.00 Harry H Joh Construction, Inc. 4 Celina Suarez
L-21-2010-DBB-2-A Governor Dr and Lakewood St Traffic Signal 10/08/2021 $306,925.00 CTE inc. 4 Juan E. Espindola
K-21-2020-DBB-3

Slurry Seal Group 2122

09/24/2021 $4,210,120.00 VSS International, Inc. 4 Ron McMinn
K-21-1999-DBB-3-A Slurry Seal Group 2121 09/15/2021 $3,798,322.90 Pavement Coatings Co 3 Celina Suarez
K-21-2000-DBB-3 AC Water & Sewer Group 1056 09/14/2021 $8,899,106.32 TC Construction Company, Inc. 8 Brittany Friedenreich
K-21-1932-DB2-3-A

Botanical Building Improvements

08/24/2021 $14,261,647.00 EC Constructors Inc. 3 Rosa Riego
K-21-1974-JOC-3

JOC Electrical

08/13/2021 $4,500,000.00 CTE, Inc. 4 Celina Suarez
K-21-1867-DBB-3 Pure Water Program: Metro Biosolids Center Improvements 08/13/2021 $40,086,690.00 PCL Construction Inc 5 Rosa Riego
K-21-2028-EMR-3 Cajon Way CMP Storm Drain Emergency 08/09/2021 $1,100,000.00 Cass Arrieta N/A Rosa Riego
K-21-1976-DBB-3-A Slurry Seal Group 2025 07/29/2021 $4,032,592.55 Pavement Coatings Co 4 Celina Suarez
K-21-2002-SLS-3 SCOUP Integrated Energy Monitoring Platform 07/15/2021 $1,079,441.00 Dynaelectric N/A Ron McMinn
K-21-1997-DBB-3 Talmadge Traffic Calming & Talmadge AC Water Main Replacement 07/15/2021 $1,485,444.86 Palm Engineering Construction Co., Inc. 8 Rosa Riego

* NTE - Not-to-Exceed

 

Additional Resources

Prevailing Wage Program