Street Reconstruction Group 1801

Project Description

This project provides for improving portions of Gold Coast Drive, between Camino Ruiz and Thanksgiving Lane, and Parkdale Avenue, between Northup Drive and Mira Mesa Boulevard. Improvements will include pavement reconstruction; replacement of traffic signal detection loops, traffic striping/markings and damaged sidewalks; installation of curb ramps to facilitate access for persons with disabilities, curb and gutter and cross gutters, bus stop pads and drain pipes; and tree removal. Before construction on the improvements, multiple underground utilities from San Diego Gas & Electric, AT&T and Spectrum Charter Communications will need to be relocated. View the project alignment.

Prior to awarding the construction contract, the City coordinated with all private utility owners in the right of way by providing them the plans illustrating the estimated location of work along the alignment. The private utility owners who acknowledged conflicts with their utility worked with the City to relocate their assets to avoid conflicts prior to construction. Extensive work was performed by AT&T, SDG&E and Charter Communications, who realigned their utilities. Once construction began, additional utilities in conflict with the project were discovered, which triggered more relocation work. This utility conflict relocation work has added extra time to the project. The private utility owners currently in conflict did not inform the City of any issues during our early design coordination phase and their as-builts did not reflect there were these additional issues.

Current Work (Updated June 18)

Gold Coast Drive:

Gold Coast Drive paving preparatory work began June 13 and will continue through July 11 at the following locations:

  • Saluda Avenue to Camino Ruiz: 6/13-6/18
  • Thanksgiving Lane to Baywood Lane: 6/20-6/24
  • Saluda Avenue to San Ramon Drive: 6/25-6/27
  • Baywood Lane to Lipscomb Drive: 6/27-7/2
  • San Ramon Drive to Westonhill Drive: 7/3-7/8
  • Westonhill Drive to Lipscomb Drive: 7/9-7/11

     

Gold Coast Drive paving work is scheduled to begin June 23 and will continue through July 29 at the following locations:

  • Saluda Avenue to Camino Ruiz: 6/23-7/1
  • Thanksgiving Lane to Baywood Lane: 6/30-7/9
  • Saluda Avenue to San Ramon Drive: 7/7-7/15
  • Baywood Lane to Lipscomb Drive: 7/14-7/22
  • San Ramon Drive to Westonhill Drive: 7/21-7/29
  • Water main relocation work has been completed at Gold Coast Court and work at Gold Coast Way began on June 16. Once water line relocation work is complete, installation of new storm drains will take place along Gold Coast Drive from Lipscomb Drive and Westonhill Drive and along Westonhill Drive between Pagoda Way and Gold Coast Drive.

     

Parkdale Avenue:

Paving work at Parkdale Avenue has completed and remaining traffic striping will be completed June 20.

Anticipated Schedule & Projected Budget

An anticipated schedule and projected budget are available on the CIP project look up page.

Community Outreach

  • Nov. 5, 2018: Informational update on Gold Coast Drive & Parkdale Avenue repairs
  • Nov. 15, 2021: Mira Mesa Community Planning Group meeting presentation
  • Aug. 15, 2022: Mira Mesa Community Planning Group meeting presentation
  • Aug. 29, 2022: PDF icon Virtual workshop