Villa La Jolla Drive Drainage System Emergency
Emergency Update
Oct. 18, 2024
Construction crews have completed the installation of the outer shoring walls at the project site. Work is now underway to excavate the damaged storm drain 40 feet below the ground.
Beginning Saturday, Oct. 19, crews will begin weekend work. The new work schedule is 7 a.m. to 7 p.m., seven days a week. Extended hours, including night work, may occur as needed to expedite the project.
Sept. 25, 2024
Aug. 9, 2024
Construction crews are preparing to begin work to repair the damaged 12-foot diameter storm drain 40 feet below the ground. To repair the pipe, they will start by relocating an existing 16-inch waterline, then construct a concrete junction box for the storm drain system and repair the pipe from the inside by lining it. After the storm drain work, they will restore the street, sidewalk and other surface improvements. Work is expected to begin in the next few weeks.
July 5, 2024
Traffic is currently flowing like normal on Villa La Jolla Drive near La Jolla Village Drive after construction crews installed a temporary bridge over the damaged 12-foot diameter storm drain. Previously, the northbound lanes of Villa La Jolla Drive approaching the intersection with La Jolla Village Drive were partially closed due to the damaged storm drain and a sinkhole that opened up as a result.
This temporary bridge will be in place for approximately two months while the contractor prepares for the full construction project. Prior to the start of construction, additional notices will be issued to residents and businesses near the impacted area.
Project Description
An aged section of a 12-foot storm drain under Villa La Jolla Drive near La Jolla Village Drive recently collapsed, resulting in a sinkhole. Emergency work is being completed to repair a section of the damaged pipe 40 feet below the ground. After the storm drain is repaired, the surrounding area, including the street, sidewalk, and other surface improvements, will be restored to its original condition.
Anticipated Schedule
- Construction start: Summer 2024.
- Construction end: Fall 2025.*
Anticipated Work
- Construction will take place along Villa La Jolla Drive near the intersection with La Jolla Village Drive.
- Before work on the 12-foot storm drain can begin, the contractor will be relocating an existing 16-inch water line that is currently in the area of the necessary storm drain repairs. Crews will also be excavating and installing shoring, dewatering and storm drain bypass systems.
- Work on the 12-foot storm drain will consist of constructing a concrete box, repairing the damaged storm drain and restoring the site, including the street and sidewalk, to its original condition.
- Temporary partial and occasional full closures of Villa La Jolla Drive in the area of the damaged storm drain are expected.
- Working hours are 7 a.m. to 7 p.m., seven days a week. Work that requires street closures will happen at night. Work on this project may occur outside of standard construction days and hours to allow the project to progress safely and efficiently.
Contact Us
For questions about this project, contact community liaison Paula Roberts from Aqua Community Relations Group at 619-794-6406 or email paula@aquacrg.com. Please reference "Villa La Jolla Drive Drainage System Emergency" in your inquiry.
*Anticipated schedule is subject to change.