Chollas Triangle Park
Project Overview
The project is currently funded for the General Development Plan (GDP) only. The project involves the vacation of Chollas Parkway, conversion of the vacated right of way to dedicated parkland, and creation of an approved GDP for a neighborhood park.
Scope of Work
The project includes obtaining an approved GDP for a new Chollas Triangle Park. The park will be developed on a triangular parcel surrounded by Chollas Parkway, 54th Street and University Avenue. The project will vacate Chollas Parkway between University Avenue and 54th Street to allow for the park's development. Park amenities to be determined during the community input process, including active and passive uses such as children's play areas, walking paths, flexible turf areas, a community event space and picnic areas.
Anticipated Schedule & Projected Budget
An anticipated schedule and projected budget are available on the CIP project look up page. Additional information is detailed below.
- City-hired design consultant in January 2021.
- Community workshop process March 2021–December 2021.
- Start environmental review January 2022.
- Park & Recreation Board approval of GDP in November 2022.
Project Files
- Chollas Triangle Park - GDP
- March 17, 2021 - Colina Del Sol Recreation Advisory Group
- July 21, 2021 - Colina Del Sol Recreation Advisory Group
- Nov. 17, 2021 - Colina Del Sol Recreation Advisory Group
Contact Us
For questions about this project, contact the Engineering & Capital Projects Department at 619-533-4207, email engineering@sandiego.gov or submit your inquiry online. Please reference "Chollas Triangle Park" in your inquiry.