Project Overview

The Sorrento Mesa Recycled Water Pipeline project will install approximately 1.25 miles of 8-inch polyvinyl chloride (PVC) water pipeline in the Sorrento Mesa community of San Diego City Council District Six. Construction will take place on segments of Morehouse Dr., Lusk Blvd., Barnes Canyon Rd., Pacific Heights Blvd., Pacific Center Dr. and McKellar Court. View a map of the project footprint.

The new recycled water pipeline system will help users conserve water by providing recycled water for irrigation and water-cooling uses.

The project will also:

  • Install laterals to connect properties to the new recycled water pipeline;
  • Use best management practices (BMPs) for erosion control, storm drain inlet protection and restoration of disturbed areas to their original condition;
  • Resurface streets impacted by its construction activities; and
  • Install new curb ramps that will improve mobility access for people with physical disabilities.

Email Updates

All efforts will be taken to minimize impacts to the businesses and residents in the community. The impacts may change as construction progresses. To help keep the community informed about the anticipated construction activities, updates will be emailed to subscribers as significant events occur.

To receive the email updates, submit your email address in the "Join our Email List" box on the left side of this page, and select the "Project Updates: Sorrento Mesa Recycled Water Pipeline" email self-subscribe list. To view previous email updates for this project, please visit the email archive page.

Construction Schedule

  • Construction Start - November 2015*
  • Construction Completion - May 2016*

Project Budgets

The project's planning, design, and construction budget is approximately $2,297,400*

*The construction schedule and project budget is approximate and subject to change.

Contact Us