Skip to main content

Capital Improvements Program (CIP)

Old Town Improv 1

Project Description

This project will replace about 4,560 linear feet (.87 miles) of 6-, 8- and 10-inch AC water main pipe with PVC mains and abandon 596 linear feet of existing 6- and 8-inch AC water mains in and around Old Town. Crews will also resurface approximately 4,842 linear feet (.92 miles) of streets by either asphalt overlay or slurry seal and curb ramps will be upgraded to meet ADA requirements, where required.

These upgrades will improve the water delivery system reliability for the Old Town area, reduce overall maintenance needs and costs, substantially reduce the potential for failure, repairs or service interruptions, and enhance safety by providing ADA accessible pathways.

Anticipated Schedule 

  • Construction start: August 2023.*
  • Construction end: August 2024.*

Project Budget  

The project's budget is $3.7 million.*

Additional budget and schedule information are available here.

Current Work (Updated Feb. 28)

  • Night work began on San Diego Avenue the week of Feb. 26. Trenching in the area will begin the week of March 4.
  • Temporary water shutdowns are scheduled for the area. Impacted homes and businesses will receive door hangers before the scheduled shutdown.
  • Day work will continue on Congress Street and Hortensia Street for meter box installation and utility verification.

Community Outreach

Contact Us

For questions about this project, contact the community liaison, Kleinfelder Construction Services, at 619-512-5905 or the Engineering & Capital Projects Department by emailing engineering@sandiego.gov or submitting your inquiry online. Please reference "Old Town Improv 1" in your inquiry.

*Anticipated schedule and project budget are subject to change.