Street Reconstruction Group 1801

Project Description

This project provides for improving portions of Gold Coast Drive, between Camino Ruiz and Thanksgiving Lane, and Parkdale Avenue, between Northup Drive and Mira Mesa Boulevard. Improvements will include pavement reconstruction; replacement of traffic signal detection loops, traffic striping/markings and damaged sidewalks; installation of curb ramps to facilitate access for persons with disabilities, curb and gutter and cross gutters, bus stop pads and drain pipes; and tree removal. Before construction on the improvements, multiple underground utilities from San Diego Gas & Electric, AT&T and Spectrum Charter Communications will need to be relocated. View the project alignment

Anticipated Schedule 

  • Construction start: Fall 2022.*
  • Construction end: Summer 2024.*

Project Budget  

The project's budget is $15.2 million.*

Current Work (Updated March 21)

  • Due to unforeseen conditions and challenges in utility coordination efforts, work on the project has been delayed. Construction is now expected to be completed in the summer of 2024.
  • Weeks of March 18 and 25: Construction activities continue to move forward as the City and contractor work to resolve unforeseen conditions on the project.

Community Outreach

  • Nov. 5, 2018: Informational update on Gold Coast Drive & Parkdale Avenue repairs
  • Nov. 15, 2021: Mira Mesa Community Planning Group meeting presentation
  • Aug. 15, 2022: Mira Mesa Community Planning Group meeting presentation
  • Aug. 29, 2022: PDF iconVirtual workshop

Additional Resources

Contact Us

For questions about this project, contact the Engineering & Capital Projects Department at 619-533-4207, email engineering@sandiego.gov or submit your inquiry online. Please reference "Street Reconstruction Group 1801" in your inquiry.

*Anticipated schedule and project budget are subject to change.