University Avenue Mobility Project
Project Background
The City of San Diego is modifying the roadway segment of University Avenue between Florida Street and Boundary Street/I-805 to improve safety and mobility along the University Avenue corridor for pedestrians, bicyclists, transit and automobile traffic.
Project Overview
The University Avenue Mobility Project (UAMP) will construct multi-modal improvements along University Avenue, between Florida Street and Boundary Street, within the North Park community. UAMP improvements include:
- Roadway Improvements, such as traffic signals, raised medians, turn pockets and re-striping.
- Transit Improvements, such as transit-only lanes and consolidating transit stops.
- Pedestrian Improvements, such as enhanced pedestrian crossings and curb ramps.
The overall project is within one of the most densely populated areas in San Diego. The area includes residential neighborhoods, business districts and major arterial corridors that connect neighborhoods; as well as local streets and bicycle and pedestrian corridors.
Email Updates and Contact Information
All efforts will be taken to minimize impacts to the residents and businesses in the community. The impacts may change as construction progresses. To help keep the community informed about the anticipated construction activities and impacts for both projects, updates will be emailed to subscribers as significant events occur.
To receive the email updates, submit your email address in the "Join our email list" box on the right side of this page, and select the "Project Updates: University Avenue Mobility Project" email self-subscribe list. Email updates will be archived and available to view on the email archive page.
Schedule and Budget
As of Sept. 7, 2023, work continues at various locations along University Avenue. The project is anticipated to be completed in late 2023.
The remaining work to be completed is as follows:
- Underground electrical trenching on University Avenue near Kansas Street and Ohio Street.
- Complete conduit and concrete work on sidewalk curb ramps and signal and streetlight poles.
- Install new signs and remove conflicting signage.
- Asphalt overlay and stripe streets.
- Energize new signals.
Below is the upcoming anticipated construction schedule:
- Week of Sept. 11
- Crews will perform electrical trenching work at the intersection of University Avenue and Kansas Street.
- Week of Sept. 25
- Crews will perform electrical trenching work at the intersection of University Avenue and Ohio Street.
- Week of Oct. 23
- Crews will complete conduit and concrete work on sidewalk curb ramps and signal and streetlight poles.
- Fall 2023
- Asphalt overlay and stripe streets.
Additional schedule and budget information is available here.