De Anza Revitalization Plan

deanza logo

About the Project

De Anza Project AreaThe De Anza Revitalization Plan project is a three-year comprehensive outreach and planning program to reimagine, repurpose and revitalize the project area. This planning effort will work with the community and stakeholders to develop conceptual revitalization plan alternatives that result in a preferred plan, an amendment to the Mission Bay Park Master Plan, and an environmental impact report (EIR).

The Mission Bay Park Master Plan identifies the De Anza area as a flexible planning area in which a number of potential uses, both public and private, can be accommodated under varying intensities and configurations. The goal of the De Anza Revitalization Plan will be to create a regional amenity that is an iconic landmark destination with a diverse mix of recreational uses that serve the region.

Project Schedule

Year 1:  Project Kick-off, Existing Condition Research, Opportunities and Constraints, Public Outreach and Preparation of Concept Plan Alternatives.

Year 2: Refine Concept Plan Alternatives, Public Outreach, Selection of Preferred Concept Plan, Preparation of the Draft Amendments to the Mission Bay Park Master Plan.

Year 3: Initiate the Environmental Review Process, Complete the Final Draft Amendments to the Mission Bay Park Master Plan, Complete the Environmental Document, Public Hearings to adopt the Amendments to the Mission Bay Park Master Plan.

Next Steps

SPRING 2018

Prepare/Distribute Notice of Preparation (NOP) of a Program Environmental Impact Report (PEIR)

PEIR NOP Public Scoping Meeting (Public Meeting)

Prepare the amendment language and graphics for the Mission Bay Park Master Plan

Presentation to the Mission Bay Park Committee and the Park and Recreation Board of the draft amendment language to the Mission Bay Park Master Plan (Public Meeting – Information Item)

SUMMER 2018/FALL 2018

Preparation of the Technical Studies and draft Program Environmental Impact Report (PEIR)

WINTER 2018/SPRING 2019

Draft PEIR released for public review (45 day review period)

Presentation to the Mission Bay Park Committee and the Park and Recreation Board of the draft amendment language to the Mission Bay Park Master Plan to make a recommendation on the draft amendment (Public Meeting – Action Item)

SPRING/SUMMER 2019

Release of Final PEIR

Hearings of the City Council Committee and City Council for consideration of adoption of the amendment to the Mission Bay Park Master Plan and the PEIR (Public Meeting - Action Item)

FALL/WINTER 2019

Presentation to the California Coastal Commission for adoption of the amendment to the Mission Bay Park Master Plan and the PEIR (Public Meeting - Action Item)

Project Goals

  • Create an iconic recreation destination that maximizes the benefit offered to the region by this extraordinary waterfront amenity.
  • Provide the highest and best use of the project area to serve the needs of a broad range of local and regional users.
  • Identify a mix of uses that will provide sustainable revenue generating leaseholds for the City.

To meet these goals the City will engage the community and technical and design experts to determine the potential reuse of the project area to revitalize De Anza and surrounding areas and include a diverse mix of public recreation, camping, wetlands, and other active regional park uses.

How does the Plan relate to the Mission Bay Park Master Plan?

The project site falls within the boundaries of the adopted Mission Bay Park Master Plan – a regional park that serves all of the residents of San Diego as well as visitors.  The Revitalization Plan is subject to Park goals and objectives in the Mission Bay Park Master Plan.  The final plan shall be the basis of the amendment to the Park Master Plan. 

The Mission Bay Park Master Plan currently provides for the following land use recommendations for the DeAnza Project Area:    

  • Regional recreation needs, including Guest Housing (camping facilities and recreational vehicles) and beach access.
  • Wetlands to contribute to the Park’s water quality. 
  • Hydrologic improvements to safeguard the viability of marsh areas.
  • Trail, viewing areas, and other recreational features to enhance public use of the study area.
  • Leaseholds that support the Mission Bay recreation use.

How does the Plan relate to the ReWild Mission Bay?

The De Anza Revitalization Plan project is an effort lead by the City of San Diego to revitalize the project area to provide for the highest and best use of the area to serve the local and regional needs of the public. The ReWild project is being conducted by the San Diego Audubon Society to restore wetlands along Pacific Beach Drive and both sides of Rose Creek. Please visit the ReWild project site at rewildmissionbay.org for more information.

Public Meeting Calendar

Mission Bay Park Committee – Summary of the Meeting

Thank you to all the public members who attended the Mission Bay Park Committee meeting on Dec. 5, 2017. The two DeAnza Revitalization concept plan alternatives were presented to the Committee as an action item. The action was to recommend a preferred alternative for the basis of the amendment to the Mission Bay Park Master Plan and for the Environmental Document. The Committee’s recommendation was to move forward with the revised alternative 2 as presented to the Committee, as the basis of the EIR analysis.

PDF icon Presentaion

Mission Bay Park Committee - Action Item

December 5, 2017

The Mission Bay Park Committee meeting will be held at the Mission Bay High School auditorium on December 5, 2017 at 6pm. The two refined draft concept alternatives for the DeAnza Revitalization will be presented to the Mission Bay Park Committee for a recommendation of a preferred concept plan.

PDF icon White Paper

PDF icon Project Area

PDF icon Three Concept Drafts

PDF icon Summary of Opposition and Support

PDF icon Two Refined Concepts

PDF icon Ad Hoc Meeting 6 Summary

Parks and Recreation Board - Information Item

Thursday, November 16, 2017

Presentation of two Refined Draft Concept Alternatives to the Parks and Recreation Board.

PDF icon Presentation

Ad-Hoc Committee Meeting #6 / Open House

June 29, 2017

There was robust attendance from the the community that provided great feedback and asked many insightful questions.

The meeting began with a presentation by the Project Team that included an overview of the meeting purpose and goals and a review of the Mission Bay Master Plan Goals and Guiding Principles. In response to all the the input received from Community Workshop #3 and online engagement activities in November, where the public provided feedback on the three preliminary Draft Concept Alternatives, the Project Team provided a highlight summary of the highest supported uses and alternatives. 

After setting the stage, the Project Team provided a detailed presentation of the two Refined Draft Concept Alternatives. The Ad-Hoc Committee then had a focused discussion in response to the Refined Draft Concept Alternatives, providing comments, asking questions, and sharing their perspective.

Following the Ad-Hoc Committee meeting members of the public were invited to participate in an Open House and review the two Refined Draft Concept Alternatives in more detail. Members of the Project Team were available to meet and talk with members of the public and ask questions about the Alternatives.

PDF icon Agenda

PDF icon Handout

PDF icon Presentation

PDF icon Summary

PDF icon Boards

Alternative 1Alternative 2

Public Workshop #3

November 7, 2016

Alternative 1Alternative 2Alternative 3Community Workshop #3 meeting on November 7, 2016 began with a presentation by the Project Team that included an overview of the community outreach process conducted to-date and a detailed presentation of the three draft Concept Alternatives. The workshop then transitioned to an open house which provided attendees with the opportunity to see the draft concept alternatives up close, ask questions of the Project Team, and provide feedback on draft uses, design, and potential refinements.

PDF icon Handout

PDF icon Presentation

PDF icon Input Summary

Ad Hoc Committee Meeting #5 / Open House

June 16, 2016

The fifth Ad-Hoc Committee meeting on June 16, 2016 included an overview of activities conducted at the Community Workshop #2 and online activities, participation in a similar group design activity with the Ad-Hoc Committee that mirrored what was done at Workshop #2, and participation in an additional program prioritization dot exercise with the public

PDF icon Agenda

PDF icon Presentation

PDF icon Minutes

Online Program Prioritization Activity

June - July 2016

Throughout the De Anza Revitalization Plan outreach process, the community and the Ad-Hoc Committee have provided significant feedback on amenities and programs they would like to see and focus on for the future of the De Anza project area, including participation online in the Program Prioritization Activity that mirrored the activity that took place at Workshop No. 2. 

PDF icon Table of Responses

Public Workshop #2

April 27, 2016

Community Workshop #2 on April 27, 2016 provided an opportunity to hear from the design team about the opportunities and constraints analysis findings and case studies of visionary parks and park features from around the world. Over 200 attendees came together and collaborated in groups to prioritize future programs and uses and then designed their own concept plans for De Anza.

PDF icon Agenda

PDF icon Presentation

PDF icon Summary

Ad Hoc Committee Meeting #4 / Open House

April 14, 2016

The fourth Ad Hoc Committee meeting on April 14, 2016 focused on discussion of the existing conditions and issues and constraints for natural resources and other environmental conditions, hearing about community/stakeholder-generated concepts, looking at iconic park case studies, and brainstorming and prioritizing potential uses.  PDF icon See Exiting Conditions Workbook here.

PDF icon Agenda

Ad Hoc Committee Meeting #3 / Open House

March 9. 2016

 

The third Ad Hoc Committee meeting on March 9, 2016 focused on seeking the Ad Hoc Committee’s refinement of a draft vision and guiding principles, providing existing conditions information on the transportation network, a leasehold analysis of existing leases and projected future demand, and an overview of existing uses within the project site and in the adjacent areas.

PDF icon Agenda

PDF icon Presentation

PDF icon Attachment 1 - Meeting / Date Topic Schedule

PDF icon Attachment 2 - Vision / Guiding Principles

PDF icon Attachment 3 - Existing Mobility Conditions

PDF icon Attachment 4 - Leasehold Analysis Fact Sheet

PDF icon Minutes

Ad Hoc Committee Meeting #2 / Open House

February 10, 2016

The second Ad Hoc Committee meeting on February 10, 2016 focused on seeking the Ad Hoc Committee’s refinement of a draft vision and guiding principles, providing an update on public involvement events, an overview of the Mission Bay Park Master Plan and California Coastal Act, and a discussion of the scope of the existing conditions analysis and input on issues and constraints.

PDF icon Agenda

PDF icon Mission Bay Park Master Plan Key Sheets

PDF icon Vision / Guiding Principles

PDF icon Coastal Act

PDF icon Minutes

Public Workshop #1

January 28, 2016

Workshop No. 1 on January 28, 2016 kicked off the De Anza Revitalization Plan project with the public. The workshop was conducted in an “open house” format with opportunities for public input at “topic stations.” Each topic station included short presentations and displayed relevant maps and information on focused topics, including natural resources, transportation, existing uses, economics, vision/future uses and amenities, project overview, and public information to gather initial input on key issues and priorities.

PDF icon Summary

Ad Hoc Committee Meeting #1 / Open House

December 9, 2015

The first Ad-Hoc Committee meeting on December 9, 2015 focused on introducing committee members and the community to the project. Content included a project overview (background, boundary, and key components), an overview of the public involvement plan and a preliminary brainstorming of the project vision and guiding principles.

PDF icon Bulletin

PDF icon Agenda

PDF icon Fact Sheet

PDF icon Presentation

PDF icon Summary

PDF icon Public Involvement Plan

Resources

PDF icon Mission Bay Park Master Plan

Contact Us

Robin Shifflet
Project Manager
City of San Diego - Planing Department
1010 2nd Ave, MS 413
San Diego, CA 92101 - 4155
[email protected]

 