Sidewalk Panel Replacement Expedite Program
City of San Diego Development Services Department (DSD)
The Sidewalk Replacement Expedite Program is a self-certification permit option for replacing damaged sidewalks in the Public Right of Way (ROW). To be eligible for this program, property owners must have received a Notice of Responsibility Letter from the Transportation Department or a Project Issues Report from the Development Services Department (DSD) concerning needed sidewalk repairs during a Building Permit application review. The Notice or Report informs property owners that they, instead of the City, are responsible for repairing the sidewalk. Please see documents concerning Sidewalk Maintenance Responsibilities and Sidewalk Maintenance Process and Frequently Asked Questions (FAQ) for additional information.
A ROW Permit is required to repair and/or replace a sidewalk. The approval of any sidewalk work in the ROW will be subject to the satisfaction of the City Engineer, as considered in the self-certification of the required ROW application and construction. For more information, refer to San Diego Municipal Code Chapter 12, Article 9, Division 7 (Right-of-Way Permits).
Self-certification is being used for sidewalk replacement permitting to reduce the permit timeframe, lower permit fees and eliminate the need for plans, so that property owners can more easily contract for the required sidewalk repairs. The typical plan submittal and review process is not required for this program. The typical inspection process is also not required.
Who Can Apply?
Property owners or a licensed contractor (classification A or C-8) representing property owners that have received a Notice of Responsibility Letter from the Transportation Department or a Project Issues Report from DSD concerning needed sidewalk repairs during a Building Permit application review.
Program Exclusions
Certain sidewalk repairs are not allowed through this self-certification program. A maximum of 3 sidewalk panels may be replaced. No curb modifications are allowed. No driveway modifications are allowed. If needed repairs include more than 3 panels, curb modifications, or driveway modifications, property owners must obtain a public Right-of-Way Permit for Standard Public Improvements, which requires that plans be prepared for review and approval.
Plan Your Project
Installation Standards
All public right-of-way improvements must be installed in accordance with the latest edition of the San Diego Regional Standard Drawings and Standard Specifications for Public Works Construction.
All new sidewalk panels must visually match the existing sidewalk. This includes keeping the same scoring pattern—both its layout and spacing—and replicating any original contractor stamping. In addition, the concrete color must match. If the existing panel is pink, then the new panel must also be pink. Maintaining these features ensures consistency with the surrounding sidewalk and preserves the intended look and function of the public walkway.
Contractor
All construction work in the City Public Right of Way shall be performed by a contractor licensed by the State of California with a qualified classification in accordance with the Department of Consumer Affairs Contractors State License Board. A licensed contractor (classification A or C-8) must be hired to perform the construction.
Monument Preservation
Required for All Self-Certification Applications: A completed Survey Monument Preservation Certification (DS-370) form must be submitted with every self-certification sidewalk replacement application. The form must be signed by a licensed land surveyor or an engineer authorized to perform surveys.
The Permittee shall be responsible for the cost of preserving & replacing all survey monuments destroyed by construction. If a vertical control monument is to be disturbed or destroyed, the City of San Diego field survey section shall be notified in writing at least 7 days prior to demolition/construction.
- What is a Survey Monument?
Survey monuments are physical markers that identify the location of property boundaries and other important survey reference points. They may be natural features or man-made objects. Common examples include:- Brass discs or survey markers set in concrete.
- Iron pipes, rebar, nails, or tacks placed by surveyors.
- Large rocks or boulders.
- Trees or other natural landmarks.
- River centerlines or other natural features.
- Mountain ridges or other prominent geographic features.
Because these monuments help establish legal property boundaries, they must be protected from disturbance during construction activities.
- Locating Property Corners
To locate property corners, you will need a copy of the map and/or deed that created your parcel. You may try to interpret it. However, to ensure that all monuments are in the proper location or to prepare legal maps/documentation, you need to contact a Professional Land Surveyor (or Civil Engineer Registered before 1982) licensed by the California Department of Consumer Affairs. For more information, please refer to the following:
Traffic Control
A separate Traffic Control Permit is not required for this program. Keep a safe path for people walking. If the sidewalk must be closed during the work, post a pedestrian notice at the site and keep a clear alternate route. The rules for when and how sidewalks can be closed come from three main sources: The California Manual on Uniform Traffic Control Devices, the City's Standard Drawings Appendix "A", and Standard Specifications for Public Works Construction.
Fees
Fees for Right-of-Way Permits are contained in this document: Fee/Deposit Schedule for Grading/Right-of-Way Permits & Mapping Actions. The following two non-refundable fees will be assessed for each self-certification sidewalk replacement application:
- Mapping Fee
This fee is collected to fund automation efforts and online GIS data and mapping for the DSD. - One-Hour Processing Fee
This fee is collected to cover one hour of administrative processing time. DSD utilizes an Enterprise Fund that must be fully cost-recoverable.
Submittal & Permit Requirements
- Letter of Request. This is the Notice of Responsibility Letter from the Transportation Department or a Project Issues Report from DSD.
- Supplemental Right-of-Way Application (DS-3037)
- Survey Monument Preservation Certification (DS-370) completed and signed by a licensed land surveyor or engineer authorized to perform surveys.
- Storm Water Requirements Applicability Checklist (DS-560) completed and signed.
Inspections
No formal inspection from a City Resident Engineer Inspector will be required for the work.
Self-Certification of Work Completed Email
After construction is complete, an email must be sent to DSDSidewalk@sandiego.gov to document the completion. Once the Self-Certification of Work Completed is received, DSD will file the document appropriately.
This letter must include the following:
- DSD project number and permit number. These start with PRJ and PMT, respectively.
- Property Address.
- Statement indicating that work has been completed.
- Photographs of the sidewalk must be attached to the email.
Apply for a Permit
Step 1
For new permit applications, review the User Guide – Apply for a Building Construction Permit.
Step 2
Read the
requirements for PDF file uploads.
Step 3
Obtain or complete the following documents:
- Letter of Request. This is the Notice of Responsibility Letter from the Transportation Department or a Project Issues Report from DSD.
- Supplemental Right-of-Way Application (DS-3037)
- Survey Monument Preservation Certification (DS-370) completed and signed by a licensed land surveyor or engineer authorized to perform surveys.
- Storm Water Requirements Applicability Checklist (DS-560) completed and signed.
Step 4
Step 5
When submitting plans with your application, you must check the plan sheet numbers before uploading your files.
Step 6
You will be required to upload the completed documents from Step 3.
Additional Resources
San Diego Municipal Code Sections
- Excavations in the Public ROW: Chapter 6, Article 2, Division 12
- Public ROW Permits: Chapter 12, Article 9, Division 7
- Land Development Terms and Definitions: Chapter 11, Article 3, Division 1
- Construction Permits: Chapter 12, Article 9, Division 7, §129.0710
Definitions
- Public Improvement
This is the act or result of construction, reconstruction, or repair of improvements that are for or incidental to a public purpose. - Public Right of Way (ROW)
A public easement for streets, alleys or other uses. - Permits & Inspections