Data Date: January 1, 2026

To create the print version set the font-size:0.5em on both tables. Save as PDF in Chrome; More Settings - Margins:None and Scale:85. Also change link on https://www.sandiego.gov/cip/reports to match the year if starting with quarter 1.

This page contains all Capital Improvements Program (CIP) projects anticipated to be advertised and awarded for construction in the current fiscal year listed initially in the City's Adopted CIP budget. This page is updated throughout the year with the current cost estimates and new projects to list. It also identifies which projects were already awarded to a construction contractor. In addition, some projects from the original list may roll-over to the first quarter of next fiscal year and possibly beyond due to unforeseen conditions. See Construction Contract Types for more information about delivery methods. Also, visit Bid and Contract Opportunities for projects currently in the bid and award phase For more information about this report, call (619) 533-4207 or email engineering@sandiego.gov.

DOWNLOAD - Forecast of Projects to be Awarded in Fiscal Year 2026 (Mid-Year Update)

summary by asset-managing departments is listed at the bottom of this page.

* To sort on a column, click on its heading. To sort on multiple columns, hold the Shift key while clicking.

Line NumberProject NameProject NumberAsset Managing DepartmentContract TypeEstimated Contract Cost ($)Estimated Total Project Cost ($)Fiscal Year AdvertisingQuarter AdvertisingFiscal Year AwardingQuarter Awarding
1Palm Avenue Interstate 805 InterchangeS00869TransportationAgency/ Developer Managed Built - City Paid$52,430,634$31,500,000FY25Q4FY26Q3
2Colina Del Sol Improv 1 (S)B20008Public UtilitiesDesign Bid Build$15,617,179$10,462,084FY26Q3FY26Q4
3Ocean Beach Branch LibraryS20015LibraryDesign Build$12,751,489$8,195,649FY26Q3FY26Q4
4HIDDEN TRAILS NEIGHBORHOOD PARKS00995Parks & RecreationDesign Bid Build$12,577,230$8,685,000FY25Q4FY26Q1
5Pressure Reducing Stations Upgrades Phs1B16017Public UtilitiesDesign Bid Build$12,305,000$8,600,000FY26Q3FY26Q4
6Air & Space Museum Roof ReplacementB20116General ServicesDesign Bid Build$12,198,991$9,075,000FY25Q4FY26Q4
7Sewer & AC Water Group 1055 (S)B18112Public UtilitiesDesign Bid Build$11,881,393$9,000,000FY26Q3FY26Q4
8Colina Del Sol Improv 1 (W)B20010Public UtilitiesDesign Bid Build$11,583,516$7,652,760FY26Q3FY26Q4
9Via De La Valle PipelineB22015Public UtilitiesDesign Build$10,023,393$6,788,293FY26Q2FY26Q3
10Chollas Creek Improv 1 (W)B20039Public UtilitiesJob Order Contract$9,818,519$7,297,091FY26Q2FY26Q3
11AC Overlay Group 2507B25007TransportationDesign Bid Build$9,550,000$7,955,000FY26Q1FY26Q3
12Sewer & AC Water Group 1055 (W)B18115Public UtilitiesDesign Bid Build$8,244,046$5,800,000FY26Q3FY26Q4
13Dr. Bertha O. Pendleton Park ImprovementB22047Parks & RecreationDesign Bid Build$7,852,573$5,451,882FY25Q3FY26Q1
14La Jolla Improv 3 (W)B20023Public UtilitiesDesign Bid Build$7,635,820$5,000,000FY26Q3FY26Q4
15Accelerated Sewer Referral Group 847B18183Public UtilitiesDesign Bid Build$6,855,331$3,687,264FY25Q3FY26Q1
16Jamacha Lomita Storm DrainB16094StormwaterDesign Bid Build$6,839,000$4,227,242FY25Q3FY26Q1
17AC Overlay Group 2514B25052TransportationDesign Bid Build$6,802,287$4,799,999FY26Q2FY26Q3
18City Hts Library Performance Annex ImpS23013LibraryDesign Build$6,514,956$5,417,724FY25Q3FY26Q1
19Balboa Park Golf Course ImprovementsB23071Parks & RecreationDesign Build$6,400,000$4,284,863FY25Q4FY26Q2
20Solana Highlands NP-Comfort StationS16032Parks & RecreationDesign Bid Build$6,133,600$4,461,200FY26Q2FY26Q3
214918/4980 Canterbury Dr SD EmergencyB25096StormwaterEmergency (As-needed)$6,000,000$4,750,000FY26Q1FY26Q1
22Rancho Bernardo CP Dog ParkL20000.2Parks & RecreationDesign Bid Build$5,700,000$3,411,200FY25Q4FY26Q2
23SV Dam Low Level Outlet ImprovementsB22002Public UtilitiesDesign Bid Build$5,366,555$2,500,000FY26Q2FY26Q4
24PW Genesee Avenue Median ImprovB22085Public UtilitiesDesign Bid Build$5,245,835$3,800,000FY25Q3FY26Q2
25Chollas Creek Improv 1 (S)B20038Public UtilitiesJob Order Contract$5,108,360$3,478,000FY26Q2FY26Q3
26Office Trailers ReplacementL17000.7Environmental ServicesDesign Build$5,000,000$4,500,000FY25Q3FY26Q1
27AC Overlay Group 2511B25049TransportationJob Order Contract$4,348,150$3,622,000FY25Q4FY26Q1
28Ofc. Jeremy Henwood Park Play Area ReplS25004Parks & RecreationDesign Build$4,250,000$3,069,000FY26Q3FY26Q4
29Chollas Creek Oak Park TrailS20012Parks & RecreationDesign Build$4,111,500$2,380,000FY00Q3FY26Q4
30Rose Marie Starns Parking Lot ImprvemtsB19163Parks & RecreationJob Order Contract$4,044,832$2,000,474FY26Q1FY26Q1
311687 Torrance St SD EmergencyB26050StormwaterEmergency (As-needed)$4,000,000$3,500,000FY26Q2FY26Q2
32AC Overlay Group 2508B25046TransportationJob Order Contract$3,800,000$3,014,915FY26Q2FY26Q3
33West Miramar Central Basin ExpansionB23000Environmental ServicesDesign Bid Build$3,750,000$2,900,000FY26Q2FY26Q3
34NCWRP - Chiller ReplacementB20148Public UtilitiesDesign Bid Build$3,646,276$2,575,000FY26Q1FY26Q3
35Scripps Miramar Ranch Library Roof ReplB22139General ServicesJob Order Contract$3,267,971$1,925,817FY25Q2FY26Q2
36Chicano Park Improvements Phase IIIB20060Parks & RecreationJob Order Contract$3,224,321$2,402,065FY26Q4FY26Q4
37AC Overlay Group 2509B25047TransportationJob Order Contract$3,211,846$2,411,846FY26Q2FY26Q3
38Sidewalk Replacement Group 2530 - U & MMB26003TransportationDesign Bid Build$3,100,000$1,700,000FY25Q3FY26Q4
39Police HQ Security FencingB22080General ServicesDesign Bid Build$3,014,350$1,793,082FY25Q4FY26Q1
40South Chollas Landfill Gas Collection System ImprovementsB22031Environmental ServicesDesign Bid Build$3,000,000$2,000,000FY26Q3FY26Q3
41Miramar WTP Caustic Pumping SystemB23014Public UtilitiesDesign Bid Build$2,853,250$1,317,300FY25Q4FY26Q2
42Center City Traffic Signals-15th StreetB22111TransportationDesign Bid Build$2,709,981$1,700,000FY25Q3FY26Q1
43Storm Drain Group 763B17143StormwaterDesign Bid Build$2,679,869$817,305FY25Q3FY26Q1
44Carmel Mountain TS EmergencyB26039TransportationSole Source Emergency$2,500,000$2,200,000FY26Q1FY26Q1
45Pump Station 64 Valve ReplacementB26000Public UtilitiesDesign Bid Build$2,500,000$1,400,000FY26Q2FY26Q3
46Narragansett Avenue AccessB18026Parks & RecreationJob Order Contract$2,205,772$598,314FY25Q4FY26Q3
47Signal Mods in Barrio LoganB13010TransportationJob Order Contract$2,151,901$1,287,092FY25Q2FY26Q1
48Willie Henderson Lighting UpgradesB23011Parks & RecreationDesign Bid Build$2,132,550$1,300,000FY25Q3FY26Q1
49Miramar Valve No2 ReplacementB23075Public UtilitiesJob Order Contract$2,067,521$1,200,000FY26Q4FY26Q4
5031st St @ National Ave Traffic SignalB17019TransportationDesign Bid Build$2,000,000$1,100,000FY26Q2FY26Q4
51Block 7T - Allied Gardens SL UU65B18129TransportationJob Order Contract$1,759,000$1,235,700FY26Q3FY26Q4
52Old Salt Pool Access StairsB22012Parks & RecreationJob Order Contract$1,707,194$853,808FY25Q4FY26Q3
53Terminal Parking Lot East RehabilitationB22157Economic DevelopmentJob Order Contract$1,536,487$885,967FY26Q2FY26Q3
54Mission Bl(Loring-Turquoise) Rd Imp UU30B18140TransportationDesign Bid Build$1,510,286$820,734FY26Q1FY26Q2
55Mission Blvd South Loring OverlayB24135TransportationDesign Bid Build$1,420,780$930,072FY26Q1FY26Q2
56Downtown Audibles 04th & E S29B18162TransportationDesign Bid Build$1,250,000$485,000FY25Q3FY26Q1
57Black Mountain Reservoir Spillway StairsB23110Public UtilitiesDesign Bid Build$1,200,000$639,666FY25Q4FY26Q3
58Hard Court ImprovementsB22045Parks & RecreationJob Order Contract$1,200,000$810,000FY25Q4FY26Q1
59Installation of City Owned SL 2201 (NSG)B22149TransportationJob Order Contract$1,157,000$800,000FY25Q3FY26Q1
60Cass (Grand-Pacific Bch Dr) Rd Imp UU143B18148TransportationDesign Bid Build$975,303$458,379FY26Q1FY26Q2
61AC Overlay Group 2511AB25067TransportationDesign Bid Build$945,000$632,643FY25Q4FY26Q1
62AC Overlay Group 2511CB25069TransportationDesign Bid Build$815,000$608,200FY25Q4FY26Q2
63Mt Hope Improvements 2 Federal Blvd SWRB26031Public UtilitiesJob Order Contract$750,000$595,000FY26Q3FY26Q3
64Paradise Hills Community Park TrailS24013Parks & RecreationMinor Contract$750,000$700,000FY26Q2FY26Q3
65Roswell Street OverlayB24137TransportationJob Order Contract$710,000$400,000FY26Q1FY26Q3
66AC Overlay Group 2511BB25068TransportationDesign Bid Build$622,808$687,808FY25Q4FY26Q2
67AC Overlay Group 2520 UUPB25083TransportationDesign Bid Build$523,329$523,329FY26Q1FY26Q2
68Northern Garage Dorm ReplB24015General ServicesMinor Contract$362,000$50,000FY25Q4FY26Q1
69Ruffin Canyon TrailB20104Parks & RecreationMinor Contract$311,981$90,000FY25Q4FY26Q1
70MTRP Trail System ManagementS23010Parks & RecreationMinor Contract$200,000$90,000FY25Q4FY26Q1
71Jamacha Lomita Storm Drain (P)B26015TransportationDesign Bid Build$197,881$197,881FY25Q3FY26Q1

Summary by asset-managing departments

Summary By Asset-Managing Departments

Asset-Managing DepartmentEstimated Construction Contract AwardEstimated Total Project Cost
Library$19,266,445$13,613,373
Parks & Recreation$62,801,552$40,587,806
Public Utilities$122,701,995$81,792,458
Environmental Services$11,750,000$9,400,000
Stormwater$19,818,869$13,522,734
Transportation$104,491,185$69,070,598
General Services$18,843,312$12,843,898
Economic Development$1,536,487$885,967
FY 2025 Total$361,209,845$241,716,834