(Third Quarter Update)

Data Date: April 18, 2017

This page contains all Capital Improvements Program (CIP) projects anticipated to be awarded for construction in the current fiscal year listed initially in the City'sAdopted CIP budget. This page is updated throughout the year with the current cost estimates and new projects to list. It also identifies which projects werealready awardedto a construction contractor. In addition, some projects from the original list may roll-over to the first quarter of next fiscal year and possibly beyond due to unforeseen conditions. SeeConstruction Contract Typesfor more information about delivery methods. Also, visitBid and Contract Opportunitiesfor projects currently in the bid and award phase For more information about this report, call (619) 533-4207 or emailengineering@sandiego.gov.

PDF iconPRINT - Forecast of Projects to be Awarded in Fiscal Year 2017 (Third Quarter Update) as of 4/18/2017

FileDOWNLOAD - Forecast of FY17 Projects to be Awarded (Third Quarter Update) as of 4/18/2017

Asummary by asset-managing departmentsis listed at the bottom of this page.

*To sort on a column, click on its heading. To sort on multiple columns, hold the Shift key while clicking.

Line
Number
Project
Name
Project
Number
Asset Managing
Department
Contract
Type
Estimated
Contract Cost
Estimated Total
Project Cost
Fiscal Year
Advertising
Quarter
Advertising
Award Status NEW
1 City Heights Rec Center Improvements B17040 Environmental Services Multiple Award Construction Contract $400,000 $460,000 2017 Q4 On Schedule NEW
2 Martin Luther King Jr. Rec Center Improvements B17037 Environmental Services Multiple Award Construction Contract $400,000 $460,000 2017 Q4 On Schedule NEW
3 Southeastern Division Police Sub-Station Improvements B17038 Environmental Services Multiple Award Construction Contract $400,000 $460,000 2017 Q4 On Schedule NEW
4 Mid City Division Police Sub-Station Improvements B17039 Environmental Services Multiple Award Construction Contract $400,000 $460,000 2017 Q4 On Schedule NEW
5 Fire Station 14 Roof & HVAC Replacement B13189 Fire-Rescue Design Bid Build $689,841 $1,027,000 2017 Q2 On Schedule
6 Fire Station 19 Roof & HVAC Replacement B13190 Fire-Rescue Design Bid Build $577,964 $936,000 2017 Q2 On Schedule
7 North University City Fire Station 50 S13021 Fire-Rescue Design Build $8,042,000 $14,000,000 2017 Q4 On Schedule NEW
8 La Jolla Children's Pool Lifeguard Station S00644 Fire-Rescue Design Bid Build $50,196 $60,235 2017 Q3 Awarded NEW
9 SAN YSIDRO BRANCH LIBRARY S00802 Library Design Build $10,300,000 $12,827,000 2017 Q1 Awarded
10 Mission Hills - Hillcrest Library S13022 Library Design Build $17,794,327 $17,847,523 2016 Q4 Awarded
11 Balboa Park GC Fuel Tank Installation B12019 Park & Recreation Design Bid Build $370,000 $445,405 2017 Q4 On Schedule
12 Cesar Solis Community Park S00649 Park & Recreation Design Bid Build $14,997,000 $16,800,000 2016 Q4 Awarded
13 Torrey Meadows Neighborhood Park S00651 Park & Recreation Design Bid Build $3,365,750 $7,922,755 2016 Q3 Awarded
14 Chicano Park ADA Upgrades S13003 Park & Recreation Design Bid Build $957,221 $1,410,893 2017 Q2 Awarded
15 Evans Pond Reclaimed Water Pipeline Inst S13010 Park & Recreation Design Bid Build $307,968 $427,468 2017 Q3 On Schedule
16 Chollas Lake Pk Playground Improvements S14002 Park & Recreation Design Bid Build $1,181,807 $1,739,000 2017 Q4 On Schedule
17 Mid City Skate Park-Park de la Cruz Neighborhood Park Improv S15003 Park & Recreation Design Bid Build $3,409,940 $5,094,000 2016 Q4 Awarded
18 San Ysidro Community Pk ADA Improvements S15033 Park & Recreation Design Bid Build $587,043 $870,000 2017 Q2 Awarded
19 University Village Park Tot Lot S13005 Park & Recreation Design Bid Build $389,697 $545,253 2016 Q4 Awarded
20 Linda Vista Skate Park S15008 Park & Recreation Design Bid Build $2,986,000 $3,744,995 2016 Q4 Awarded NEW
21 Del Mar Mesa Neighborhood Park Phase II S13023 Park & Recreation Design Bid Build $1,526,569 $2,226,964 2016 Q4 Awarded NEW
22 Kelly St Neighborhood Pk Security Lighting Upgrade S16016 Park & Recreation Design Bid Build $85,000 $150,000 2017 Q4 On Schedule NEW
23 Encanto Community Pk Security Lighting Upgrade S16017 Park & Recreation Design Bid Build $239,560 $404,560 2017 Q4 On Schedule NEW
24 Marie Widman Memorial Pk Sec Lighting S16018 Park & Recreation Design Bid Build $175,000 $300,000 2017 Q4 On Schedule NEW
25 Skyline Hills Community Pk Security Lighting Upgrade S16021 Park & Recreation Design Bid Build $85,000 $150,000 2017 Q4 On Schedule NEW
26 Silver Wing Pk Ballfield Lighting - Ph 2 S16051 Park & Recreation Design Bid Build $858,139 $1,138,617 2017 Q1 On Schedule NEW
27 Balboa Park Plaza de Panama L17002 Park & Recreation Design Bid Build $60,038,145 $78,108,614 2017 Q4 On Schedule NEW
28 Larsen Field ADA Improvements Phase II S13004 Park & Recreation Design Bid Build $1,099,123 $1,689,000 2016 Q3 Awarded
29 Southcrest Trails Neighborhood Park S01071 Park & Recreation Design Bid Build $1,659,956 $1,717,580 2017 Q3 Awarded NEW
30 Old Fire Station 29 Demolition & Temporary Park Improvements BM1000003-16 Park & Recreation Design Bid Build $397,953 $750,000 2017 Q3 Awarded NEW
31 Police Range Refurbishment S10118 Police Design Bid Build $846,718 $1,078,000 2016 Q4 Awarded
32 Police HQ Co-Generation Repower Project Phase II S10131 Police Design Bid Build $922,134 $1,854,653 2016 Q4 Awarded
33 Sewer & AC Water Group 764A (S) B00380 Public Utilities Design Bid Build $2,691,518 $4,112,092 2017 Q2 On Schedule
34 Sewer & AC Water Group Job 776 (S) B00387 Public Utilities Design Bid Build $5,912,086 $8,495,523 2017 Q2 Awarded
35 Sewer Group 818 B00414 Public Utilities Design Bid Build $1,987,864 $3,330,921 2017 Q2 Awarded
36 SPS 13 14 16 25A & 85 Dual FM B00501 Public Utilities Design Bid Build $3,095,480 $3,646,480 2017 Q4 On Schedule
37 La Jolla Country Club Reservoir B11024 Public Utilities Design Bid Build $5,215,000 $8,505,000 2017 Q3 On Schedule
38 Water Group Job 952 B11048 Public Utilities Design Bid Build $2,952,000 $4,082,681 2017 Q4 On Schedule
39 CI - Water and Sewer Group Job 966 (W) B12086 Public Utilities Design Bid Build $1,447,100 $2,122,400 2018 Q1 On Schedule
40 Tyrian St/Soledad Ave Sewer Main Replace B12111 Public Utilities Design Bid Build $643,536 $1,346,500 2016 Q3 Awarded
41 Sewer Group 835 B13157 Public Utilities Design Bid Build $2,501,955 $3,741,840 2017 Q1 Awarded
42 Water and Sewer GJ 955 (W) B13186 Public Utilities Design Bid Build $2,719,392 $3,973,952 2017 Q2 On Schedule
43 Sewer & AC Water Group 776 (W) B13197 Public Utilities Design Bid Build $1,787,914 $2,678,464 2017 Q2 Awarded
44 Sewer & AC Water Group 764A (W) B13201 Public Utilities Design Bid Build $1,212,402 $1,767,738 2017 Q2 On Schedule
45 Sewer and AC Water Group 837 (S) B13214 Public Utilities Design Bid Build $1,452,000 $2,206,461 2017 Q3 Awarded
46 Pipeline Rehabilitation AE-1 B14030 Public Utilities Design Bid Build $4,394,017 $6,988,558 2017 Q2 Awarded
47 S Mission Valley TS Accelerated Project B14068 Public Utilities Design Bid Build $378,659 $600,000 2016 Q4 Awarded
48 Water and Sewer Group 955 (S) B14069 Public Utilities Design Bid Build $504,300 $738,700 2017 Q2 On Schedule
49 Water Group 969 B14100 Public Utilities Design Bid Build $1,000,000 $1,686,100 2017 Q4 On Schedule
50 SPS 23T - Reliability Improvements B14131 Public Utilities Design Bid Build $1,400,000 $1,911,000 2017 Q4 On Schedule
51 SPS 76 Generator B14168 Public Utilities Design Bid Build $41,500 $75,000 2017 Q4 On Schedule
52 AC Water & Sewer Group 1011 (S) B15040 Public Utilities Design Bid Build $750,000 $977,500 2017 Q4 On Schedule
53 AC Water & Sewer Group 1011 (W) B15041 Public Utilities Design Bid Build $6,899,000 $8,295,950 2017 Q4 On Schedule
54 Sewer and AC Water Group 837 (W) B15071 Public Utilities Design Bid Build $1,418,901 $2,249,851 2017 Q3 Awarded
55 AC Water & Sewer Group 1017 (S) B15116 Public Utilities Design Bid Build $79,373 $188,442 2017 Q3 On Schedule
56 AC Water & Sewer Group 1017 (W) B15119 Public Utilities Design Bid Build $5,745,671 $7,924,255 2017 Q3 On Schedule
57 Otay Valley Manhole Improvements Phase 3 B15123 Public Utilities Design Bid Build $310,369 $406,250 2016 Q4 Awarded
58 AC Water and Sewer Group 1029 (S) B15172 Public Utilities Multiple Award Construction Contract $995,000 $1,326,000 2017 Q1 On Schedule
59 AC Water and Sewer Group 1029 (W) B15174 Public Utilities Multiple Award Construction Contract $5,140,000 $6,854,000 2017 Q1 On Schedule
60 Pipeline Rehabilitation AI-1 B15187 Public Utilities Design Bid Build $4,256,683 $4,986,045 2017 Q1 Awarded
61 Pipeline Rehabilitation AJ-1 B15201 Public Utilities Design Bid Build $4,092,518 $4,898,092 2017 Q1 Awarded
62 Remaining Small Diameter CI Water Ph I B15206 Public Utilities Design Bid Build $2,474,500 $3,518,500 2017 Q4 On Schedule
63 Tyrian St/Soledad Ave & AC Wtr Main (W) B15216 Public Utilities Design Bid Build $770,364 $982,000 2016 Q3 Awarded
64 Pipeline Rehabilitation AM-1 B16002 Public Utilities Design Bid Build $4,664,125 $6,075,331 2017 Q1 Awarded
65 PS2 Power Reliability & Surge Protection S00312 Public Utilities Design Bid Build $56,228,000 $72,100,800 2017 Q1 On Schedule
66 WDSU - Reservoirs & Dams - Ph II S11106 Public Utilities Design Build $10,000,000 $12,049,028 2017 Q4 On Schedule
67 69th & Mohawk Pump Station S12011 Public Utilities Design Bid Build $11,000,000 $15,088,594 2017 Q1 On Schedule
68 Tierrasanta (Via Dominique) Pump Station S12040 Public Utilities Design Bid Build $10,995,000 $14,319,186 2016 Q4 Awarded
69 Chollas Building S11025 Public Utilities Design Build $29,585,997 $37,856,871 2016 Q2 Awarded
70 MOC 5 Materials Bins B14133 Public Utilities Design Bid Build $477,045 $760,000 2017 Q1 Awarded
71 SBWRP Loop Control System & Valve Master Station Improvements B16132 Public Utilities Design Build $724,488 $900,000 2017 Q3 On Schedule
72 Water & Sewer Group 965 (W) B12057 Public Utilities Design Bid Build $2,463,903 $3,199,547 2017 Q3 On Schedule
73 Water & Sewer Group 965 (S) B12048 Public Utilities Design Bid Build $2,468,103 $3,147,585 2017 Q3 On Schedule
74 Pipeline Rehabilitation AG1 B14118 Public Utilities Design Bid Build $3,360,977 $5,434,000 2017 Q2 Awarded
75 Water and Sewer Group 954(S) B13203 Public Utilities Design Bid Build $751,367 $971,407 2016 Q4 Awarded
76 Water and Sewer Group 954(W) B10187 Public Utilities Design Bid Build $3,005,466 $3,763,530 2016 Q4 Awarded
77 Tecolote Canyon Sewer B11111 Public Utilities Design Bid Build $518,000 $1,143,662 2016 Q3 Awarded
78 Sewer and Water Group 701 (S) B00452 Public Utilities Design Bid Build $3,590,850 $5,365,000 2016 Q3 Awarded
79 Sewer and Water Group 701 (W) B00039 Public Utilities Design Bid Build $751,352 $1,037,000 2016 Q3 Awarded
80 AC Water Group 1018A B16146 Public Utilities Design Bid Build $5,796,313 $8,371,352 2017 Q3 On Schedule
81 Otay 2nd Pipeline Phase 2 B15046 Public Utilities Design Build $9,170,000 $12,227,000 2017 Q2 On Schedule
82 AC Woodman St. Pipeline Replacement B15081 Public Utilities Design Build $2,126,000 $2,834,000 2017 Q2 On Schedule
83 AC Water & Sewer Group 1025 (S) B15082 Public Utilities Design Bid Build $185,674 $349,899 2017 Q3 On Schedule NEW
84 AC Water & Sewer Group 1025 (W) B15083 Public Utilities Design Bid Build $6,546,486 $7,872,700 2017 Q3 On Schedule NEW
85 AC Water Group 1031 B16036 Public Utilities Design Bid Build $3,302,113 $4,993,958 2017 Q2 Awarded NEW
86 Priority Sewer Main Replacement Group 16 B16018 Public Utilities Multiple Award Construction Contract $8,336,427 $12,592,494 2017 Q2 On Schedule NEW
87 Bayview Reservoir Solar Project S14021 Public Utilities Design Build $712,893 $2,325,000 2017 Q1 Awarded NEW
88 MOC Complex Solar Project S14022 Public Utilities Design Build $1,894,327 $2,675,000 2017 Q1 Awarded NEW
89 Emergency Strobe Lights at MBC, NC, SB B13227 Public Utilities Design Bid Build $404,996 $768,995 2017 Q3 On Schedule NEW
90 Stadium Wetland Mitigation 21003814 Public Utilities Design Bid Build $3,741,518 $5,044,170 2016 Q4 Awarded NEW
91 SEWER and AC Water GROUP 764 (S) B00368 Public Utilities Design Bid Build $1,530,495 $2,334,561 2017 Q3 On Schedule NEW
92 Sewer & AC Water Group 821(S) B00413 Public Utilities Design Bid Build $1,855,652 $2,863,267 2017 Q3 On Schedule NEW
93 SEWER and AC Water GROUP 764 (W) B15106 Public Utilities Design Bid Build $1,592,964 $2,257,713 2017 Q3 On Schedule NEW
94 Sewer & AC Water Group 821 (W) B15107 Public Utilities Design Bid Build $1,396,302 $1,908,824 2017 Q3 On Schedule NEW
95 Bay Bridge Community Center ADA B13076 Public Works - General Services Design Bid Build $331,858 $608,000 2016 Q4 Awarded
96 SY Comm and Rec CTR-ADA Barrier Removal B13078 Public Works - General Services Design Bid Build $761,991 $1,240,000 2016 Q4 Awarded
97 Carmel Valley Rec Ctr ADA Access Impr B14152 Public Works - General Services Design Bid Build $470,000 $673,000 2017 Q1 On Schedule
98 Carmel Creek Park Comft St ADA Access Im B14153 Public Works - General Services Design Bid Build $159,185 $234,000 2017 Q2 On Schedule
99 Carmel Del Mar Comft St ADA Access Impro B14154 Public Works - General Services Design Bid Build $317,200 $431,000 2017 Q1 On Schedule
100 ADA Accessibility Improvements Group I B15222 Public Works - General Services Design Build $1,318,553 $2,175,756 2017 Q3 On Schedule
101 ADA Accessibility Improvements Group II B15229 Public Works - General Services Design Build $1,107,447 $1,968,629 2017 Q2 On Schedule
102 ADA Accessibility Improvements Group IV B15230 Public Works - General Services Design Bid Build $411,950 $620,000 2017 Q2 On Schedule
103 Colina Del Sol Pool ADA B13077 Public Works - General Services Design Bid Build $443,823 $836,477 2016 Q2 Awarded
104 Pioneer Park and Comfort Station B12005 Public Works - General Services Design Build $201,002 $535,086 2016 Q3 Awarded NEW
105 Memorial Park Community Building Clearance Activity S15039 Public Works - General Services Design Bid Build $370,527 $426,106 2017 Q1 Awarded NEW
106 Barrio Youth Facilities 2 & 3 B13067 Public Works - General Services Design Bid Build $546,267 $967,371 2016 Q3 Awarded NEW
107 City Heights Youth & Community Center AD B13068 Public Works - General Services Design Bid Build $284,678 $563,962 2016 Q1 Awarded NEW
108 Marston House Roof Replacement B16038 Public Works - General Services Design Bid Build $385,000 $462,000 2016 Q2 Awarded NEW
109 Carmel Mountain Library Roof Replacement B16043 Public Works - General Services Design Bid Build $530,000 $651,562 2016 Q2 Awarded NEW
110 ADA Imp & Exp of Paradise Senior Center S15002 Public Works - General Services Design Bid Build $295,000 $700,000 2017 Q2 On Schedule NEW
111 Pacific Beach Library Roof & HVAC B16045 Public Works - General Services Design Build $1,701,850 $1,830,480 2017 Q2 On Schedule NEW
112 Tierrasanta Rec Center Roof & HVAC B16046 Public Works - General Services Design Build $930,852 $1,000,000 2017 Q2 On Schedule NEW
113 Beta Street and 37th Street Green Alley B11057 Transportation & Storm Water Design Bid Build $537,048 $786,959 2017 Q1 Awarded
114 Bonillo Dr (4150) Storm Drain Replace B12033 Transportation & Storm Water Design Bid Build $223,045 $497,045 2016 Q3 Awarded
115 Camino del Este Path Xing Improvements B13088 Transportation & Storm Water Design Bid Build $302,542 $449,640 2017 Q4 On Schedule
116 Burroughs & W Dunlop Sts Storm Dr Repl B13101 Transportation & Storm Water Design Bid Build $443,824 $878,733 2017 Q1 Awarded
117 El Cajon & 59th Obstruction DIF CR DS B13105 Transportation & Storm Water Design Bid Build $202,133 $324,833 2016 Q4 Awarded
118 Southeastern Obstruction DIF 13 CR B13106 Transportation & Storm Water Design Bid Build $62,735 $240,800 2016 Q4 Awarded
119 Group Job 13I North Park DIF CR B13111 Transportation & Storm Water Design Bid Build $125,235 $474,500 2017 Q2 Awarded
120 Group Job 13J Peninsula DIF CR B13112 Transportation & Storm Water Design Bid Build $385,203 $737,500 2016 Q4 Awarded
121 Sunset Cliffs 3 SL Circuit Upgrade B13141 Transportation & Storm Water Design Bid Build $643,138 $943,500 2017 Q2 Awarded
122 Whitney Ct (6969) Storm Drain Replacement B13210 Transportation & Storm Water Design Bid Build $227,150 $681,695 2017 Q2 Awarded
123 New Streetlights - 19 Locations B14012 Transportation & Storm Water Design Bid Build $275,500 $389,200 2017 Q1 Awarded
124 Bikeway Striping Improvements-Citywide B14040 Transportation & Storm Water Design Bid Build $1,000 $10,000 2017 Q3 On Schedule
125 Golden Hill CR Obstruction DIF 14 B14052 Transportation & Storm Water Design Bid Build $107,628 $250,500 2017 Q1 Awarded
126 City Street Lights - 25 Locations B14106 Transportation & Storm Water Design Bid Build $220,600 $275,300 2016 Q4 Awarded
127 Alamo, Salvation, 68th Street Basins LID B14120 Transportation & Storm Water Design Bid Build $2,174,000 $3,000,000 2017 Q4 On Schedule
128 Division St @ Valencia Pky TS B15008 Transportation & Storm Water Design Bid Build $206,155 $275,000 2017 Q4 On Schedule
129 Guardrail Projects Group 1501 B15224 Transportation & Storm Water Design Bid Build $64,980 $242,000 2017 Q2 Awarded
130 Euclid Ave & Home Improvements S00886 Transportation & Storm Water Design Bid Build $60,000 $985,820 2017 Q1 On Schedule
131 La Jolla Mesa Drive Sidewalk S00928 Transportation & Storm Water Design Bid Build $574,900 $826,000 2017 Q3 On Schedule
132 Bikeway Striping Improvements-Citywide S00955 Transportation & Storm Water Design Bid Build $73,500 $97,000 2017 Q3 On Schedule
133 Trojan Ave 56th to 60th UUD B00718 Transportation & Storm Water Design Bid Build $44,301 $228,825 2017 Q3 Awarded
134 Sunset Cliffs Dr Coronado to Newport UUD B00720 Transportation & Storm Water Design Bid Build $256,122 $305,771 2017 Q3 On Schedule
135 Fanual Street Phase II Grand to Reed UUD B00722 Transportation & Storm Water Design Bid Build $85,813 $180,000 2017 Q3 Awarded
136 San Vicente Street to Ashmore UUD B00725 Transportation & Storm Water Design Bid Build $48,100 $187,817 2017 Q3 Awarded
137 San Vicente Street to Ashmore UUD B00725 Transportation & Storm Water Design Bid Build $38,312 $149,597 2017 Q1 Awarded NEW
138 Moraga Ave to Idelwild UUD B00726 Transportation & Storm Water Design Bid Build $185,896 $304,173 2017 Q3 On Schedule
139 Moraga Ave Ph II -Moraga Ct to Monair UUD B00788 Transportation & Storm Water Design Bid Build $189,809 $275,450 2017 Q3 On Schedule
140 District 1 Block 1-J UUD B00836 Transportation & Storm Water Design Bid Build $137,536 $161,808 2017 Q4 On Schedule
141 District 4 Block 4-Z UUD B00838 Transportation & Storm Water Design Bid Build $445,780 $610,768 2017 Q3 On Schedule
142 District 7 Block 7-A UUD (Street Lighting only) B00842 Transportation & Storm Water Design Bid Build $160,000 $192,000 2017 Q3 Awarded NEW
143 Altadena/Wightman/Winona-El Cajon UUD B00850 Transportation & Storm Water Design Bid Build $87,196 $277,867 2017 Q3 Awarded
144 Euclid Ave UUD Streetlights (Euclid-Univ) (Street Lighting only) B11131 Transportation & Storm Water Design Bid Build $60,000 $72,000 2017 Q3 Awarded NEW
145 Block 7R Allied Gardens UUD B12064 Transportation & Storm Water Design Bid Build $773,955 $1,000,355 2017 Q3 On Schedule
146 Lincoln Av UUD (30th St-Wabash Av) B12066 Transportation & Storm Water Design Bid Build $72,250 $85,000 2017 Q3 On Schedule
147 Potomac St UUD (Calle Tres Lomas-Sea Breeze) B12069 Transportation & Storm Water Design Bid Build $210,126 $229,625 2017 Q3 On Schedule
148 32nd Street UUD (Market St - F St) B13144 Transportation & Storm Water Design Bid Build $80,750 $95,000 2017 Q4 On Schedule
149 Cardiff Street UUD (Carlisle Dr - Wade St) B13145 Transportation & Storm Water Design Bid Build $52,800 $134,000 2017 Q1 Awarded
150 Howard Avenue UUD (Park Bl - I-805) B13146 Transportation & Storm Water Design Bid Build $342,550 $403,000 2017 Q4 On Schedule
151 Mount Alifan Dr UUD (Genesee Ave-Mt Everest Blvd) B13148 Transportation & Storm Water Design Bid Build $57,753 $153,000 2017 Q1 Awarded
152 Paradise Valley Rd UUD (Potomac St-Parkland Wy) B13149 Transportation & Storm Water Design Bid Build $9,800 $104,000 2017 Q1 Awarded
153 28th Street UUD (Island Av - Clay St) B13156 Transportation & Storm Water Design Bid Build $114,500 $176,000 2017 Q1 Awarded
154 25th (SB) Street UUP (Coronado-SB to Grove) - 20A B15088 Transportation & Storm Water Design Bid Build $30,600 $36,000 2017 Q4 On Schedule
155 32nd Street UUP (Market to Imperial) - 20A B15089 Transportation & Storm Water Design Bid Build $61,200 $72,000 2017 Q4 On Schedule
156 Woodrow Ave UUP (Calvacado to Aemacost) - 20A B15091 Transportation & Storm Water Design Bid Build $45,498 $54,000 2017 Q1 Awarded
157 Wightman Street UUP (Chamoune to Euclid) - 20A B15092 Transportation & Storm Water Design Bid Build $61,200 $72,000 2017 Q4 On Schedule
158 Seminole Drive UUP (Stanley to Estelle) - 20A B15093 Transportation & Storm Water Design Bid Build $38,250 $45,000 2017 Q4 On Schedule
159 Mission Blvd UUP (Loring to Tourquoise) - 20A B15094 Transportation & Storm Water Design Bid Build $76,500 $90,000 2017 Q4 On Schedule
160 Hilltop Drive UUP (Boundary to Toyne) - 20A B15095 Transportation & Storm Water Design Bid Build $107,100 $126,000 2017 Q4 On Schedule
161 Hancock Street UUP (Witherby to Tourquoise) - 20A B15096 Transportation & Storm Water Design Bid Build $53,550 $63,000 2017 Q4 On Schedule
162 30th Street Phase III Broadway to K UUD B00717 Transportation & Storm Water Design Bid Build $286,722 $322,882 2017 Q3 On Schedule
163 Mission Village-Ronda to Qualcomm Sdwk B15004 Transportation & Storm Water Design Bid Build $705,100 $1,085,000 2017 Q4 On Schedule
164 Grove Ave/Ingrid Ave@Hollister St TS B13179 Transportation & Storm Water Design Bid Build $151,187 $349,500 2017 Q1 Awarded
165 31st St @ Ocean View Bl Traffic Signal B14014 Transportation & Storm Water Design Bid Build $199,041 $260,000 2017 Q4 On Schedule
166 41st St @ National Ave Traffic Signal B14016 Transportation & Storm Water Design Bid Build $173,287 $330,000 2017 Q2 Awarded
167 Campanile Dr & Montezuma Rd Signal Mod B13134 Transportation & Storm Water Design Bid Build $118,800 $155,200 2016 Q4 Awarded
168 Callado Rd Green St Infiltration BMP B13198 Transportation & Storm Water Design Bid Build $1,000,000 $1,650,000 2017 Q4 On Schedule
169 3rd Ave @ Washington St Traffic Signal B14062 Transportation & Storm Water Design Bid Build $163,787 $395,100 2017 Q1 Awarded
170 Block 2S1 South Mission Beach UUD B12067 Transportation & Storm Water Design Bid Build $363,800 $428,000 2017 Q4 On Schedule
171 Illion Street UUD (Gardena Av - Milton St) B13147 Transportation & Storm Water Design Bid Build $44,079 $125,000 2017 Q1 Awarded
172 District 2 Block 2-T UUD B00835 Transportation & Storm Water Design Bid Build $1,054,787 $2,022,709 2016 Q4 Awarded NEW
173 NATL Ave (32nd to 43rd) UUD B00787 Transportation & Storm Water Design Bid Build $589,923 $1,315,107 2016 Q4 Awarded NEW
174 30th St PH 3A 20A B00719 Transportation & Storm Water Design Bid Build $219,008 $540,513 2016 Q4 Awarded NEW
175 District 4 Block 4AA UUD B00826 Transportation & Storm Water Design Bid Build $1,264,553 $2,503,304 2016 Q4 Awarded NEW
176 District 2 Block 2-E UUD B00709 Transportation & Storm Water Design Bid Build $1,270,150 $4,622,791 2016 Q4 Awarded NEW
177 Mission Hills/Presidio Circuit Upgrades B15234 Transportation & Storm Water Design Bid Build $480,000 $480,000 2016 Q4 Awarded NEW
178 District 8 Block 8-F UUD B00714 Transportation & Storm Water Design Bid Build $76,770 $92,124 2016 Q4 Awarded NEW
179 Asphalt Overlay 1508 B15181 Transportation & Storm Water Design Bid Build $4,840,880 $5,000,000 2016 Q4 Awarded NEW
180 State Route 163 Friars S00851 Transportation & Storm Water Design Bid Build $609,852 $658,640 2017 Q1 Awarded NEW
181 Mission Gorge Road Settlement Emergency B16181 Transportation & Storm Water Design Bid Build $4,500,000 $6,000,000 2017 Q1 Awarded NEW
182 Emergency Storm Channel Debris & Sediment Clearing at Smythe Channel Culverts 12004365 Transportation & Storm Water Design Bid Build $750,000 $750,000 2017 Q1 Awarded NEW
183 Flashing Crosswalks Group 1501 B15017 Transportation & Storm Water Design Bid Build $263,131 $580,000 2017 Q1 Awarded NEW
184 Ulric St - Fashion Hills to David St K-Rail B13163 Transportation & Storm Water Design Bid Build $683,730 $1,018,100 2017 Q1 Awarded NEW
185 El Cajon Blvd. Median Improvements S00826 Transportation & Storm Water Design Bid Build $296,347 $500,000 2017 Q1 Awarded NEW
186 31st Street UUD (Market St - L St) B13143 Transportation & Storm Water Design Bid Build $2,281 $18,000 2017 Q1 Awarded NEW
187 Toyon Rd (5655) Storm Drain Replacement B13117 Transportation & Storm Water Design Bid Build $300,675 $650,000 2017 Q2 Awarded NEW
188 AC Overlay Group 1511, JOC7 (Bond#3 + 100K) B15183 Transportation & Storm Water Design Bid Build $5,000,000 $6,000,000 2017 Q3 On Schedule NEW
189 Concrete Street Panel Group 1501 B15199 Transportation & Storm Water Design Bid Build $2,535,505 $3,300,000 2016 Q4 Awarded NEW
190 AC Overlay Street Paving Group 1601 B16024 Transportation & Storm Water Design Bid Build $5,800,000 $6,848,824 2017 Q4 On Schedule NEW
191 Concrete Street Panel Group 1601 B16026 Transportation & Storm Water Design Bid Build $3,260,098 $3,346,685 2017 Q4 On Schedule NEW
192 Sidewalk Replacement Group 1602 B16028 Transportation & Storm Water Design Bid Build $1,162,500 $1,200,000 2017 Q4 On Schedule NEW
193 Sidewalk Replacement Group 1603 B16029 Transportation & Storm Water Design Bid Build $871,500 $900,000 2017 Q4 On Schedule NEW
194 Sidewalk Replacement Group 1604 B16030 Transportation & Storm Water Design Bid Build $888,960 $918,000 2017 Q2 On Schedule NEW
195 Emergency Construction Services for 202 Coast Blvd Beach Access Stair Replacement B17029 Transportation & Storm Water Design Bid Build $350,000 $490,000 2017 Q2 Awarded NEW
196 City Heights Pedestrian Improvements (P1-P8 & East Euclid Ave) S15044 Transportation & Storm Water Design Bid Build $2,480,243 $4,800,000 2017 Q2 Awarded NEW
197 El Cajon Boulevard Pedestrian Improvement B15210 Transportation & Storm Water Design Bid Build $496,355 $1,260,000 2017 Q2 Awarded NEW
198 Girard @ Pearl A P S La Jolla DIF 13 B13104 Transportation & Storm Water Design Bid Build $26,248 $210,500 2017 Q1 Awarded NEW
199 Emergency Construction Services for Sorrento & Alvarado Creek Concrete Channel Emergency Repairs 21003729 Transportation & Storm Water Design Bid Build $1,250,000 $1,250,000 2017 Q2 Awarded NEW
200 Repairs at a Storm Drainage Pipe at 2582 Manzana Way B17079 Transportation & Storm Water Design Bid Build $100,000 $140,000 2017 Q3 Awarded NEW
201 AC Overlay Group 1509, JOC5 (Bond#3 + 100K) B15182 Transportation & Storm Water Design Bid Build $1,233,246 $6,000,000 2017 Q3 Awarded NEW
202 AC Overlay Group 1512, JOC8 (Bond#3 + other balances) B15184 Transportation & Storm Water Design Bid Build $4,499,970 $6,000,000 2017 Q2 Awarded NEW
203 Sidewalk Replacement Group 1601 B16027 Transportation & Storm Water Design Bid Build $836,257 $1,136,257 2017 Q2 Awarded NEW
204 Emergency Repairs: Storm Drain Pipe at 10818 Eberly Court B17106 Transportation & Storm Water Design Bid Build $235,000 $325,000 2017 Q3 Awarded NEW
205 Emergency Repairs: Storm Drain Pipe at 4128 Casita Way B17107 Transportation & Storm Water Design Bid Build $300,000 $375,000 2017 Q3 Awarded NEW
206 Emergency Repairs: Storm Drain Pipe at 3337 Buena Vista Street B17109 Transportation & Storm Water Design Bid Build $325,000 $400,000 2017 Q3 Awarded NEW
207 Emergency Repairs: Storm Drain Pipe at 5006 Collwood Way B17117 Transportation & Storm Water Design Bid Build $75,000 $150,000 2017 Q3 Awarded NEW
208 Emergency Repairs: Storm Drain Pipe at 3215 Talbot Street B17108 Transportation & Storm Water Design Bid Build $100,000 $130,000 2017 Q3 Awarded NEW
209 Avenida De La Playa Storm Drain Reconstruction S13018 Transportation & Storm Water Design Bid Build $591,383 $11,362,508 2017 Q2 Awarded NEW
210 Emergency Repairs: Storm Drain Pipe at 9109 Hector Avenue B17099 Transportation & Storm Water Design Bid Build $2,000,000 $2,300,000 2017 Q3 Awarded NEW
211 Uptown Traffic Signal Upgrades B14010 Transportation & Storm Water Design Bid Build $25,000 $159,500 2017 Q3 Awarded NEW
212 Asphalt Overlay Group 1502 B15130 Transportation & Storm Water Design Bid Build $11,406,644 $13,000,000 2015 Q3 Awarded NEW

Summary By Asset-Managing Departments

Asset-Managing Department Estimated Construction Contract Award Estimated Total Project Cost*
Airports $0 $0
Environmental Services $1,600,000 $1,840,000
Fire-Rescue $9,360,001 $16,023,235
Library $28,094,327 $30,674,523
Office of the Chief Operating Officer $0 $0
Park & Recreation $94,716,871 $125,635,104
Police $1,768,852 $2,932,653
Public Utilities $263,445,935 $357,246,769
Public Works - General Services $10,567,183 $15,923,429
QUALCOMM Stadium $0 $0
Special Promotional Programs $0 $0
Transportation & Storm Water $77,094,362 $122,104,325
FY 2017 Total** $486,647,531 $672,380,038

**Includes projects awarded and projects anticipated to be awarded this FY 2017, and projects anticipated to be awarded 1st Quarter FY 2018.

Archive of Anticipated CIP Projects