(Second Quarter)

Data Date: February 15, 2019

To create the print version set the font-size:0.5em on both tables. Save as PDF in Chrome; More Settings - Margins:None and Scale:85

This page contains all Capital Improvements Program (CIP) projects anticipated to be advertised and awarded for construction in the current fiscal year listed initially in the City'sAdopted CIP budget. This page is updated throughout the year with the current cost estimates and new projects to list. It also identifies which projects werealready awardedto a construction contractor. In addition, some projects from the original list may roll-over to the first quarter of next fiscal year and possibly beyond due to unforeseen conditions. SeeConstruction Contract Typesfor more information about delivery methods. Also, visitBid and Contract Opportunitiesfor projects currently in the bid and award phase For more information about this report, call (619) 533-4207 or emailengineering@sandiego.gov.

PDF iconPRINT - Forecast of Projects to be Awarded in Fiscal Year 2019 (Second Quarter Update) as of 2/15/2019

FileDOWNLOAD - Forecast of Projects to be Awarded (Second Quarter Update) as of 2/15/2019

Asummary by asset-managing departmentsis listed at the bottom of this page.

*To sort on a column, click on its heading. To sort on multiple columns, hold the Shift key while clicking.

Line
Number
Project
Name
Project
Number
Asset Managing
Department
Contract
Type
Estimated
Contract
Cost ($)
Estimated
Total Project
Cost ($)
Fiscal Year
Advertising
Quarter
Advertising
Fiscal Year
Awarding
Quarter
Awarding
1 Carmel Creek Park Comft St ADA Access Im B14153 ADA Compliance and Accessibility Department Job Order Contract $246,947 $454,000 2017 Q2 2019 Q1
2 William Heath Davis House ADA Accessibil B15223 ADA Compliance and Accessibility Department Job Order Contract $202,994 $528,200 2018 Q4 2019 Q2
3 ADA Accessibility Improvements Group IV B15230 ADA Compliance and Accessibility Department Job Order Contract $371,040 $710,879 2019 Q1 2019 Q2
4 Group Job 13F Linda Vista DIF CR B13108 ADA Compliance and Accessibility Department Design Bid Build $166,921 $504,429 2018 Q3 2019 Q1
5 ADA S/W La Jolla Shore & Calle Corta B16101 ADA Compliance and Accessibility Department Design Bid Build $281,000 $661,800 2019 Q2 2019 Q4
6 ADA APS GROUP 2E - Washington St B16099 ADA Compliance and Accessibility Department Design Bid Build $349,622 $488,664 2019 Q3 2019 Q4
7 MYF Electrical System Upgrade B18034 Airports Department Job Order Contract $252,440 $420,000 2019 Q3 2019 Q4
8 Brown Field CBP Modular Structure 21003798 Airports Department Sole Source $1,884,200 $2,939,000 2019 Q3 2019 Q4
9 Canyonside Community Park Improvements S12004 Development Services Department Design Bid Build $1,023,833 $1,401,126 2019 Q3 2019 Q4
10 Fire-Rescue Air Operations Facility S15012 Fire-Rescue Department Design Bid Build $3,214,544 $4,923,601 2018 Q4 2019 Q1
11 San Diego Central Library-Boiler Replac B17103 Library Department Job Order Contract $1,003,000 $1,600,000 2019 Q2 2019 Q3
12 Tierrasanta Library Expansion S15011 Library Department Job Order Contract $800,000 $1,619,000 2018 Q3 2019 Q1
13 Ladera St Beach Access Stairway Coastal Bluff Stabilization B19009 Parks & Recreation Department Emergency $51,037 $101,037 2018 Q4 2019 Q3
14 Chollas Community Park Comfort Station S16058 Parks & Recreation Department Design Bid Build $2,267,803 $3,360,838 2019 Q1 2019 Q3
15 California Tower Seismic Retrofit L12003.2 Parks & Recreation Department Design Bid Build $4,753,500 $5,748,550 2019 Q1 2019 Q3
16 Bay Terrace Senior Center S16060 Parks & Recreation Department Design Bid Build $3,484,865 $6,383,376 2018 Q4 2019 Q3
17 Skyline Hills Community Pk Security Lighting Upgrade S16021 Parks & Recreation Department Job Order Contract $103,445 $220,000 2018 Q1 2019 Q1
18 Doyle Community Park ADA Upgrade S15037 Parks & Recreation Department Job Order Contract $290,132 $688,445 2019 Q1 2019 Q4
19 Kelly St Neighborhood Pk Security Lighting Upgrade S16016 Parks & Recreation Department Job Order Contract $109,975 $190,000 2018 Q1 2019 Q1
20 Tierrasanta Sports Field Lighting Ph II S18004 Parks & Recreation Department Design Bid Build $128,031 $209,855 2018 Q4 2019 Q1
21 Casa de Balboa Fire Alarm System B17181 Parks & Recreation Department Job Order Contract $850,000 $1,588,000 2019 Q4 2019 Q4
22 Marie Widman Memorial Pk Sec Lighting S16018 Parks & Recreation Department Job Order Contract $297,752 $475,000 2018 Q1 2019 Q1
23 Orchard Av, Capri by Sea & Old Salt Pool B14073 Parks & Recreation Department Job Order Contract $333,057 $647,883 2018 Q2 2019 Q1
24 Skyline Hills Community Park ADA Improve S15038 Parks & Recreation Department Design Bid Build $1,674,620 $2,859,854 2019 Q1 2019 Q1
25 North Park Mini-park and Streetscape Imp S10050 Parks & Recreation Department Design Bid Build $1,998,884 $3,484,003 2019 Q4 2019 Q4
26 EB Scripps Park Comfort Stn Replacement S15035 Parks & Recreation Department Design Bid Build $3,148,000 $4,697,000 2019 Q2 2019 Q3
27 Rolling Hills Neighborhood Park ADA Upgrade S15021 Parks & Recreation Department Design Bid Build $1,537,650 $2,028,182 2018 Q4 2019 Q1
28 Rancho Mission Neigh Pk Play Area Upgrade S15004 Parks & Recreation Department Design Bid Build $1,650,868 $2,324,695 2018 Q4 2019 Q1
29 Chimney Canyon Slope Restoration B18110 Parks & Recreation Department Job Order Contract $555,582 $638,582 2018 Q2 2019 Q2
30 Dennery Ranch Neighborhood Park S00636 Planning Department Agency/Developer/Managed Built - City Paid $5,070,000 $15,100,000 2019 Q2 2019 Q3
31 Police Range Refurbishment Phase II S18005 Police Department Design Bid Build $8,009,753 $9,100,000 2019 Q3 2019 Q4
32 Sewer Pump Station 33 Demolition B16104 Public Utilities Department Design Bid Build $313,000 $475,000 2019 Q2 2019 Q3
33 AC Water & Sewer Group 1027 (S) B15118 Public Utilities Department Design Bid Build $30,100 $40,200 2019 Q4 2019 Q4
34 Water and Sewer Group 967 (S) B15145 Public Utilities Department Design Bid Build $64,000 $100,000 2019 Q2 2019 Q4
35 South Bay Wtr Recl Plant Manhole Rehab B18086 Public Utilities Department Job Order Contract $179,405 $400,000 2019 Q3 2019 Q3
36 AC Water & Sewer Group 1042 (S) B17176 Public Utilities Department Design Bid Build $371,300 $776,100 2019 Q3 2019 Q4
37 SEWER GROUP JOB 830 B11019 Public Utilities Department Design Bid Build $411,400 $604,000 2019 Q2 2019 Q3
38 SEWER & AC Water Group 797(S) B00398 Public Utilities Department Design Bid Build $675,840 $948,224 2019 Q3 2019 Q4
39 Pipeline Rehabilitation AP-1 B17064 Public Utilities Department Design Bid Build $2,027,182 $3,118,420 2019 Q1 2019 Q2
40 Ultraviolet Disinfection System Replace B18031 Public Utilities Department Design Bid Build $2,600,000 $4,520,000 2019 Q3 2019 Q4
41 Sewer and AC Water Group 807 (S) B00403 Public Utilities Department Design Bid Build $2,714,998 $4,685,468 2019 Q2 2019 Q4
42 Pipeline Rehabilitation AO-1 B16161 Public Utilities Department Design Bid Build $3,074,886 $4,972,525 2019 Q1 2019 Q2
43 Pipeline Rehabilitation AU-1 B18037 Public Utilities Department Design Bid Build $3,346,618 $4,729,165 2019 Q2 2019 Q3
44 Sewer & AC Water Group 697A (S) B00346 Public Utilities Department Design Bid Build $3,858,141 $5,253,657 2019 Q1 2019 Q3
45 Pipeline Rehabilitation AS-1 B17184 Public Utilities Department Job Order Contract $4,585,082 $9,028,457 2018 Q4 2019 Q1
46 Pipeline Rehabilitation AL-1 B16001 Public Utilities Department Design Bid Build $5,865,000 $7,156,000 2019 Q3 2019 Q4
47 Mira Mesa Trunk Sewer Improvement B16056 Public Utilities Department Design Bid Build $6,173,717 $7,077,776 2019 Q1 2019 Q3
48 Sewer & AC Water Crown Point West (S) B16145 Public Utilities Department Design Bid Build $6,663,931 $10,234,622 2019 Q4 2019 Q4
49 AC Water & Sewer Group 1013 (S) B15147 Public Utilities Department Design Bid Build $1,302,654 $1,611,654 2019 Q3 2019 Q4
50 MBC Cooling Water System Chiller Upgrade B16165 Public Utilities Department Design Bid Build $2,637,000 $3,771,000 2019 Q2 2019 Q4
51 Pipeline Rehabilitation AT-1 B17187 Public Utilities Department Design Bid Build $5,341,000 $6,520,000 2018 Q4 2019 Q2
52 Manzana Water Replacement B18109 Public Utilities Department Design Bid Build $600,000 $900,000 2019 Q4 2019 Q4
53 Water Group 967 B12058 Public Utilities Department Design Bid Build $489,000 $795,000 2019 Q2 2019 Q4
54 Hotel Circle CI & AC Accelerated Replacement B18235 Public Utilities Department Design Bid Build $1,200,000 $1,620,000 2019 Q3 2019 Q4
55 Sewer & AC Water Group 697A (W) B15207 Public Utilities Department Design Bid Build $1,273,682 $1,899,111 2019 Q1 2019 Q3
56 Sewer & AC Water Group 797 (W) B16129 Public Utilities Department Design Bid Build $1,347,032 $1,978,696 2019 Q3 2019 Q4
57 Remaining Small Diameter CI Water Ph 3 B17091 Public Utilities Department Design Bid Build $1,800,000 $2,665,000 2019 Q3 2019 Q4
58 Otay WTP-Basin #1 Concrete Restoration B17092 Public Utilities Department Design Bid Build $1,938,355 $2,650,000 2019 Q1 2019 Q3
59 AC Water & Sewer Group 1042 (W) B17177 Public Utilities Department Design Bid Build $3,502,000 $5,162,000 2019 Q3 2019 Q4
60 AC Water Group 1030 B16042 Public Utilities Department Design Bid Build $4,343,118 $5,865,455 2019 Q4 2019 Q4
61 AC Water & Sewer Group 1027 (W) B15121 Public Utilities Department Design Bid Build $4,892,700 $6,523,600 2019 Q4 2019 Q4
62 Sewer & AC Water Crown Point West (W) B16144 Public Utilities Department Design Bid Build $5,312,067 $7,286,814 2019 Q4 2019 Q4
63 Otay 2nd Pipeline Phase 1 B14092 Public Utilities Department Design Bid Build $5,889,000 $7,832,000 2019 Q3 2019 Q4
64 Sewer & AC Water Group 807 (W) B16087 Public Utilities Department Design Bid Build $6,246,200 $6,590,108 2019 Q2 2019 Q4
65 Remaining Small Diameter CI Water Ph2 B16023 Public Utilities Department Design Bid Build $7,779,750 $11,312,800 2019 Q3 2019 Q4
66 Otay 1st/2nd PPL West of Highland Avenue S12016 Public Utilities Department Design Bid Build $21,080,400 $29,440,500 2019 Q3 2019 Q4
67 Montezuma PPL/Mid City Pipeline Ph 2 S11026 Public Utilities Department Design Bid Build $24,143,000 $31,555,000 2019 Q3 2019 Q4
68 NCWRP Expansion (Pkg. 4) B15142 Public Utilities Department Design Bid Build $13,038,300 $15,689,300 2019 Q2 2019 Q4
69 North City Pure Water Facility (Pkg. 1) B15139 Public Utilities Department Design Bid Build $2,695,000 $2,695,000 2019 Q2 2019 Q4
70 AC Water & Sewer Group 1013 (W) B15156 Public Utilities Department Design Bid Build $11,723,882 $14,131,036 2019 Q3 2019 Q4
71 Palm Avenue Transitional Housing S18003 Real Estate Assets Department Design Bid Build $5,397,073 $6,500,000 2018 Q4 2019 Q1
72 101 Ash Improvements S17009 Real Estate Assets Department Design Bid Build $17,080,261 $25,880,408 2018 Q3 2019 Q1
73 Euclid Ave & Home Improvements S00886 Transportation & Storm Water Department Job Order Contract $76,676 $1,029,415 2017 Q1 2019 Q1
74 Ashley Falls Lg Scale Storm Flow Storage B14007 Transportation & Storm Water Department Design Bid Build $581,391 $1,451,500 2019 Q3 2019 Q4
75 Hayes Ave Storm Drain S11002 Transportation & Storm Water Department Design Bid Build $746,832 $1,320,100 2018 Q3 2019 Q1
76 Manzana Storm Drain Replacement B17079 Transportation & Storm Water Department Design Bid Build $853,000 $1,250,000 2019 Q3 2019 Q4
77 Van Dyke Ave (4481) Storm Drain Replacem B12034 Transportation & Storm Water Department Design Bid Build $979,078 $1,987,918 2018 Q4 2019 Q2
78 Highland & Monroe Aves Storm Drain Repl B12096 Transportation & Storm Water Department Design Bid Build $1,586,000 $2,168,871 2019 Q3 2019 Q4
79 Alamo, Salvation, 68th Street Basins LID B14120 Transportation & Storm Water Department Design Bid Build $2,047,000 $2,943,666 2019 Q3 2019 Q4
80 Famosa Slough Salt Marsh Creation S00605 Transportation & Storm Water Department Sole Source $170,000 $488,000 2019 Q2 2019 Q2
81 Morena Bl & W. Bernardo Medians B15015 Transportation & Storm Water Department Job Order Contract $124,889 $433,261 2019 Q3 2019 Q4
82 Pacific Hwy & W Palm St Signal Mod B13008 Transportation & Storm Water Department Job Order Contract $160,000 $279,200 2018 Q4 2019 Q1
83 Del Sol Boulevard-Central S00858 Transportation & Storm Water Department Design Bid Build $166,236 $5,511,297 2019 Q1 2019 Q3
84 41st St @ National Ave Traffic Signal B14016 Transportation & Storm Water Department Job Order Contract $180,641 $378,011 2019 Q2 2019 Q3
85 Jackson Dr & Winding Creek Dr TS B15009 Transportation & Storm Water Department Design Bid Build $229,875 $321,088 2019 Q3 2019 Q4
86 32nd & Norman Scott Rd TS Upgrade B15005 Transportation & Storm Water Department Design Bid Build $240,000 $375,000 2019 Q3 2019 Q4
87 Uptown CMP SD Lining B16091 Transportation & Storm Water Department Design Bid Build $288,000 $584,000 2019 Q3 2019 Q4
88 W Bernardo @ Technology Traffic Signal B17156 Transportation & Storm Water Department Design Bid Build $328,300 $479,700 2019 Q2 2019 Q3
89 Ash St & Richmond St Sidewalks B15026 Transportation & Storm Water Department Design Bid Build $346,500 $707,770 2019 Q3 2019 Q4
90 Camino del Este Path Xing Improvements B13088 Transportation & Storm Water Department Design Bid Build $360,000 $507,098 2019 Q1 2019 Q3
91 Sidewalk Replacement Group 1603 B16029 Transportation & Storm Water Department Design Bid Build $881,231 $1,200,000 2018 Q4 2019 Q1
92 Sidewalk Replacement Group 1604 B16030 Transportation & Storm Water Department Design Bid Build $1,010,000 $1,418,000 2019 Q3 2019 Q3
93 Balboa Avenue Corridor Improvements S00831 Transportation & Storm Water Department Design Bid Build $1,394,999 $2,981,887 2018 Q4 2019 Q2
94 Downtown Complete Streets Implementation (DMP Phase 1 & 2 Cycle Track Interim Implementation) B17056 Transportation & Storm Water Department Design Bid Build $2,011,720 $31,571,100 2019 Q4 2019 Q2
95 Asphalt Resurfacing Group 1702 (Option C) B17095 Transportation & Storm Water Department Design Bid Build $4,756,087 $5,500,000 2019 Q3 2019 Q3
96 Concrete Street Panel Group 1601 B16026 Transportation & Storm Water Department Design Bid Build $2,535,450 $3,331,305 2018 Q3 2019 Q1
97 31st Street UUD (Market St - L St) B13143 Transportation & Storm Water Department Job Order Contract $14,000 $18,000 2019 Q3 2019 Q3
98 25th (SB) Street UUP (Coronado-SB to Gro B15088 Transportation & Storm Water Department Job Order Contract $30,600 $36,000 2019 Q3 2019 Q4
99 Seminole Drive UUP (Stanley to Estelle) B15093 Transportation & Storm Water Department Job Order Contract $38,250 $45,000 2019 Q3 2019 Q4
100 Coronado SB (27th-Madden) SL UU193 - 5 lights B17008 Transportation & Storm Water Department Job Order Contract $54,000 $60,000 2019 Q3 2019 Q4
101 Cass St (Grand-Pacific) SL UU143 - 6 lights B17007 Transportation & Storm Water Department Job Order Contract $64,800 $72,000 2019 Q3 2019 Q4
102 Cardiff St (Wade-Carlisle) Rd Imp UU10 B17069 Transportation & Storm Water Department Design Bid Build $66,968 $90,407 2019 Q1 2019 Q3
103 Hughes St (58th St-Jodi St) SL UU101 - 11 lights B17010 Transportation & Storm Water Department Job Order Contract $118,800 $132,000 2019 Q3 2019 Q4
104 Illion St (Gardena-Milton Rd) Imp UU624 B17072 Transportation & Storm Water Department Design Bid Build $131,289 $177,240 2019 Q1 2019 Q3
105 Woodrow (Calvocado-Armacost) Rd Imp UU16 B17097 Transportation & Storm Water Department Design Bid Build $153,146 $206,748 2019 Q1 2019 Q3
106 Block 2S1 South Mission RD IMP UU977_RP B18152 Transportation & Storm Water Department Job Order Contract $157,911 $213,180 2019 Q1 2019 Q3
107 Mt Alifan (Genesee-Mt Everst) Rd Imp UU21 B17073 Transportation & Storm Water Department Design Bid Build $170,214 $229,789 2019 Q1 2019 Q3
108 Hilltop Drive UUP (Boundary to Toyne) B15095 Transportation & Storm Water Department Job Order Contract $189,555 $208,455 2018 Q4 2019 Q2
109 Block7-O1 B18143 Transportation & Storm Water Department Design Bid Build $290,113 $391,653 2019 Q2 2019 Q4
110 Block 4-J1 UUD (Mid City) B13152 Transportation & Storm Water Department Job Order Contract $324,000 $405,000 2019 Q3 2019 Q4
111 28th St (Island Av-Clay St) Rd Imp UU9 B17070 Transportation & Storm Water Department Design Bid Build $445,776 $601,797 2019 Q1 2019 Q3
112 Block 7G2 UUP - CIP B15085 Transportation & Storm Water Department Design Bid Build $497,213 $1,053,390 2018 Q3 2019 Q2
113 Block 8R UUP - CIP B15097 Transportation & Storm Water Department Design Bid Build $965,280 $1,580,133 2019 Q2 2019 Q4
114 Block 3HH (Talmadge 3) Rd Imp UU352 B17068 Transportation & Storm Water Department Design Bid Build $1,025,387 $1,384,273 2019 Q1 2019 Q3
115 Block 8A (Golden Hill) Rd Imp UU494 B17074 Transportation & Storm Water Department Design Bid Build $1,051,414 $1,419,409 2019 Q1 2019 Q3
116 Block 7G2 21003598 Transportation & Storm Water Department Design Bid Build $7,679,523 $10,453,837 2018 Q3 2019 Q2
117 Block 8R UUP 21003599 Transportation & Storm Water Department Design Bid Build $7,821,865 $10,670,343 2019 Q2 2019 Q4

Summary By Asset-Managing Departments

Asset-Managing Department Estimated Construction Contract Award Estimated Total Project Cost
ADA Compliance and Accessibility Department $1,618,524 $3,347,972
Airports Department $2,136,640 $3,359,000
Development Services Department $1,023,833 $1,401,126
Fire-Rescue Department $3,214,544 $4,923,601
Library Department $1,803,000 $3,219,000
Parks & Recreation Department $23,235,201 $35,645,300
Planning Department $5,070,000 $15,100,000
Police Department $8,009,753 $9,100,000
Public Utilities Department $171,528,740 $232,613,688
Real Estate Assets Department $22,477,334 $32,380,408
Transportation & Storm Water Department $43,344,010 $97,666,840
FY 2019 Total $283,461,578 $438,756,935

Archive of Anticipated CIP Projects